exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 75 discussion

Actual exam question from PMI's PMP
Question #: 75
Topic #: 1
[All PMP Questions]

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path.
What should the project manager do?

  • A. Report the delay with rectifying actions to the project management office (PMO).
  • B. Rebaseline the project schedule to absorb the delay.
  • C. Notify the project steering committee about the cause of the delay.
  • D. Report the delay with rectifying actions to the change control board (CCB) for review.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
bug_bloke
Highly Voted 4 months, 3 weeks ago
Selected Answer: D
Reporting to the PMO (option A) might be necessary, but it may not directly address the quality problem causing the rework on the critical path. The PMO could be informed of the situation separately, but the immediate concern is to address the quality problem. Rebaselining the project schedule (option B) could be considered after addressing the quality problem, but it doesn't directly solve the root cause of the delay. Notifying the project steering committee (option C) is important to keep stakeholders informed, but the immediate concern is to rectify the quality problem and minimize the rework. Reporting the delay with rectifying actions to the change control board (CCB) for review (option D) is the most appropriate action in this scenario. The CCB is responsible for reviewing and approving changes to the project scope, schedule, and resources. By involving the CCB, the project manager can seek support for rectifying the quality problem and explore potential solutions to get the project back on track.
upvoted 13 times
...
Pilot
Highly Voted 5 months ago
quality problem -> corrective action -> change request -> CCB
upvoted 11 times
...
a7medsmt
Most Recent 3 weeks, 3 days ago
A is correct we need to correct quality problem dont need to make changes may be use fast track or crashing so no need to CCB
upvoted 2 times
...
Lucky_Cindy
3 months ago
D is correct
upvoted 1 times
...
jukaz365
3 months, 3 weeks ago
The answer is C. First Project Manager needs to identify root House of the problem. Then develop rectifying action and then communicate to stakeholders. Prioritize critical path activities. If changes to the schedule - then CBB
upvoted 2 times
...
Asakthi
4 months, 2 weeks ago
A. Report first
upvoted 1 times
...
GinniSingh
5 months, 1 week ago
Selected Answer: A
quality problem is generally defects which are never a change, so should not go to CCB. Instead the rectifying actions, post RCA should be shared with PMO
upvoted 1 times
...
r60380
5 months, 2 weeks ago
Selected Answer: D
Rectifying actions is a change that needs CCB for approval before taking proposed rectify actions
upvoted 2 times
...
smartrammy
5 months, 3 weeks ago
Selected Answer: D
D. Report the delay with rectifying actions to the change control board (CCB) for review.
upvoted 2 times
...
SteAle
5 months, 4 weeks ago
Selected Answer: D
I'd go with D as its not clear what type of the organization it is and whether or not PMO plays a signifcant role in the process
upvoted 1 times
...
Drogbadrog
6 months, 1 week ago
Selected Answer: A
CCB is solely for change request
upvoted 1 times
...
deji_ebooks
6 months, 3 weeks ago
A very confusing question. The choice is clearly between A & D. D may be considered as less correct because you don't report (a problem & rectifying actions) to CCB but you make a request (for change). On the other hand, the fact that "rectifying actions" is included, this may be considered as a request for action with the problem reporting being the justification for the rectifying actions that need to be taken which makes case for D. A may be considered as being correct because the PM is reporting the problem and also proactively recommending rectifying actions. However, reporting to the PMO does not necessarily solve the problem but can only lead to steps towards correcting the problem. I would lean towards D because it's the ultimate step that has to be taken to correct the reported problem.
upvoted 3 times
...
Yuxiao
6 months, 3 weeks ago
That is not a change, so you cannot go to change control board.
upvoted 1 times
...
victory108
7 months ago
Selected Answer: D
D. Report the delay with rectifying actions to the change control board (CCB) for review
upvoted 1 times
...
EC123
7 months, 2 weeks ago
It looks like the reason of not A is because there is rectifying actions and if there is rectifying actions, that means there is change, so the first action should be reporting to CCB. Not sure if my understanding is correct.
upvoted 2 times
...
FlowlineHemanth
7 months, 3 weeks ago
Selected Answer: A
no it cant go to CCB since change is not by any stakeholders. it is due quality issues which repeating. So escalate to pmo
upvoted 2 times
...
Hung3102
9 months, 1 week ago
C seems correct
upvoted 1 times
Hung1
8 months, 1 week ago
Change answer to D
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago