Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 59 discussion

Actual exam question from PMI's PMP
Question #: 59
Topic #: 1
[All PMP Questions]

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?

  • A. A predictive execution strategy
  • B. An iterative execution strategy
  • C. An agile execution strategy
  • D. A hybrid execution strategy
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PMPStudent
Highly Voted 1 year, 9 months ago
Selected Answer: D
I would go with D. Because there is a already a date specified to enforce the regulation and also because the regulation requirements are only known at a very high level.
upvoted 11 times
...
NejibELOUNI
Most Recent 1 month, 2 weeks ago
la bonne reponse c'est: B d'apres le mindset PMI
upvoted 1 times
...
martinx84
3 months, 1 week ago
Selected Answer: D
Regulation is a predictive life cycle, and uncertain is Agile life cycle
upvoted 1 times
...
KingSchex
7 months ago
Selected Answer: D
Answer is D. There is already a set and enforced date, but the requirements are subject to change.
upvoted 1 times
...
BuviD
8 months, 3 weeks ago
Selected Answer: D
Hybrid
upvoted 1 times
...
xcjxcj
9 months ago
Selected Answer: D
Since B and C are similar, i would choose D as answer.
upvoted 1 times
...
Lhenica
9 months, 3 weeks ago
Selected Answer: D
D is my answer
upvoted 1 times
...
GabMonterey
9 months, 3 weeks ago
Selected Answer: D
D. Since the scenario tell that its government regulation it should be predictive but since stated in scenario that changes might happen, approach should be embedded with agile. So hybrid (Predictive + Agile).
upvoted 2 times
...
RestlessMonkey
11 months, 1 week ago
I believe B (iterative) is the best approach here. You are given a release date to meet the regulation (single delivery), but the scope is unclear, so you keep correcting the scope and iterating on it until it is correct or meets the law.
upvoted 4 times
...
Davonos
1 year, 1 month ago
I would go with C. As the date of enforcement is not directly related to any project dates. But changing requirements definitely calls for Agility
upvoted 1 times
...
Hanh_Ngo
1 year, 3 months ago
A Hybrid Approach is often applied as follows: Predictive for clear/known parts and Adaptive for unclear part (uncertainty). With the given information in the Questions, we just know that "there is uncertainty", "a Date/Deadline is fixed". There is NO INFORMATION OR HINT regarding "Known parts" ==> Is there any other reason for option D????? ==> Should C best matched with the given information?
upvoted 2 times
Hanh_Ngo
1 year, 3 months ago
I found the hint and convincible reason myself for option D. It said "Company must implement REGULATION". Regulation requirement is a must, we must adhere to it => a hint of FIXED SCOPE. And Fixed Date => We cannot fully use Agile where SCOPE is not fixed. ==> We just can use some components of Agile to deal with uncertainty. ==> HYBRID Approach is best option now. (Really tricky question)
upvoted 8 times
...
...
kbrt
1 year, 3 months ago
Agile olmalı çünkü en üst düzeyde gereksinimler belirli ve çoğu da sonradan belirlenecek.
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: D
D. A hybrid execution strategy
upvoted 1 times
...
alt_coffey
1 year, 7 months ago
Selected Answer: D
Chose D. Partly because its government and they tend to be more waterfall type, but with the new unclear requirement, they can implement more agile up to a certain point. Second, since there is some guidance out there, prefer to be hybrid.
upvoted 2 times
...
Ganzee
1 year, 9 months ago
C. An agile execution strategy
upvoted 3 times
...
novantuno
1 year, 9 months ago
Selected Answer: D
Agile up to the date, then predictive
upvoted 3 times
...
cesarrsn
1 year, 10 months ago
Selected Answer: C
the uncertanty brings the need of using agile aproach
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...