Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 57 discussion

Actual exam question from PMI's PMP
Question #: 57
Topic #: 1
[All PMP Questions]

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations.
Which two tools should the project manager use to analyze team performance? (Choose two.)

  • A. Burndown chart
  • B. Product backlog burnup chart
  • C. Cumulative flow diagram of completed features
  • D. Work breakdown structure (WBS)
  • E. Project schedule
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
AbbasTaki
Highly Voted 1 year, 6 months ago
Selected Answer: AC
A. Burndown chart: The burndown chart tracks the progress of work completed against the planned work over time. It provides a visual representation of the team's progress and helps identify any deviations from the planned trajectory. By analyzing the burndown chart, the project manager can assess whether the team is falling behind, maintaining a steady pace, or accelerating, allowing them to take corrective actions if necessary. C. Cumulative flow diagram of completed features: The cumulative flow diagram tracks the flow of work items through different stages of the project. It provides a visual representation of the work in progress and can highlight bottlenecks or areas where work is piling up. By analyzing the cumulative flow diagram, the project manager can identify any blockages or inefficiencies that may be hindering the team's momentum and take steps to address them.
upvoted 14 times
...
fragar65
Most Recent 1 month, 2 weeks ago
AB - as per PMBOK Guide: Section 4.4: Performance Domain: Delivery. Burndown and Burnup Charts.
upvoted 1 times
...
23169fd
2 months, 1 week ago
Selected Answer: AC
Burndown Chart: A burndown chart shows the amount of work remaining in a sprint or project over time. It provides a visual representation of progress and can help identify if the team is on track or falling behind. If the team is losing momentum, the burndown chart can reveal trends such as work not being completed as expected within the iterations, allowing the project manager to identify potential issues and bottlenecks. Cumulative Flow Diagram of Completed Features: A cumulative flow diagram (CFD) displays the status of work items over time, showing the flow of features through different stages (e.g., to-do, in-progress, completed). It helps visualize bottlenecks, workflow issues, and trends in the team's performance. If the team is slowing down, the CFD can indicate where work is piling up, such as in the "in-progress" column, suggesting a need to adjust processes or remove obstacles.
upvoted 1 times
...
Paramak
4 months, 1 week ago
Selected Answer: AB
Burndown chart is to track progress and Product Backlog Burnup chart to track the progress made in scope.
upvoted 2 times
...
mrwriting
7 months, 1 week ago
Selected Answer: BC
B is better than A: burndown does not correctly if the scope changes
upvoted 2 times
...
58e5964
10 months ago
Selected Answer: AB
Fell for the trap myself. The explanation for C is wrong so it would not apply. Cumulative Flow diagram shows the progress of all three metrics (total, in progress and completed). Not just the completed features.
upvoted 3 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: AC
A. Burndown chart and C
upvoted 1 times
...
YUCHAN2022
10 months, 3 weeks ago
Chat GPT showed A&C
upvoted 1 times
...
Lhenica
11 months, 3 weeks ago
Selected Answer: AC
For me A&C are correct answers
upvoted 1 times
...
GabMonterey
11 months, 4 weeks ago
Selected Answer: AB
A & B is correct answer
upvoted 1 times
...
Omar_icon
1 year, 1 month ago
Selected Answer: AB
check the trend of what was done (burnup chart) and what is in progress (burndown chart) CFD will show the bottleneck not to track the progress
upvoted 1 times
...
DipeshVora
1 year, 2 months ago
Selected Answer: AB
A & B are correct.
upvoted 3 times
...
Goku_PMP
1 year, 3 months ago
Selected Answer: B
As team was performing fine in earlier iteration, the best way is to review backlog burn up. There may be chances that team is performing all the user stories, but in recent iteration UserStories might have increased. The best way is to refer backlog burn up chart
upvoted 3 times
...
vivijain
1 year, 3 months ago
Selected Answer: AC
A & C are correct.
upvoted 1 times
...
MKWONG
1 year, 4 months ago
Selected Answer: AC
agree with A, C
upvoted 1 times
...
smartrammy
1 year, 4 months ago
Selected Answer: AC
A. Burndown chart C. Cumulative flow diagram of completed features
upvoted 2 times
...
Virtuous
1 year, 4 months ago
Selected Answer: AB
The Answer should focus on Agile performance measurements
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...