Actual exam question from PMI's PMP
Question #: 355
Topic #: 1
[All PMP Questions]

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).
What should the project lead do?

  • A. Discuss the product owner's recommendations with the team and implement the agreed-on solutions
  • B. Allow the team to self-organize so one of the resources can lead the team to achieve consensus
  • C. Discuss the recommendations with the test manager and request better quality control
  • D. Facilitate the meeting so anyone can share their ideas and is heard during the session
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 3 days ago
Selected Answer: A
It’s seem to be A
upvoted 1 times
...
ompk
3 months, 3 weeks ago
D has a word "anyone" which may include customers or sponsors so A sounds better
upvoted 1 times
...
912ed99
4 months, 2 weeks ago
I will go for option A
upvoted 1 times
...
josephsafiran
8 months, 2 weeks ago
Selected Answer: D
The project lead should facilitate the meeting so anyone can share their ideas and is heard during the session (Option D). This approach encourages open communication, ensures all perspectives are considered, and fosters a collaborative environment. It’s important to remember that quality issues often arise from various factors, and it’s crucial to hear from all team members who might provide valuable insights. After the discussion, the team can decide on the best course of action, which might include a root cause analysis (RCA) or other strategies. This approach aligns with agile principles, which emphasize team collaboration and individuals’ interactions.
upvoted 2 times
...
Ngcy2023
9 months, 2 weeks ago
why C? can anyobe explain?
upvoted 1 times
...
David983
11 months ago
Selected Answer: A
I will go with A, Option D mention about facilitate the meeting but question said that meeting is already established, going with A the PO suggestion will be evaluated and the rest part of the team will provide their points of view to at the end reach an agreement.
upvoted 4 times
...
Only12go
11 months ago
Selected Answer: D
D. Facilitate the meeting so anyone can share their ideas and is heard during the session. In a situation where quality issues are preventing delivery to the client, it's crucial to conduct a root cause analysis (RCA) to identify the underlying causes of the problems. Facilitating a meeting where anyone can share their ideas and concerns is essential for a successful RCA. This approach promotes open communication and ensures that all team members have an opportunity to contribute to the identification of root causes. The project lead should act as a neutral facilitator, guiding the discussion and helping the team reach a consensus on the identified causes and potential solutions. This collaborative approach is aligned with agile principles and encourages a sense of ownership and responsibility among team members for addressing and resolving quality issues.
upvoted 3 times
...
bu02951
11 months, 1 week ago
Selected Answer: D
We already have the meeting with the project team then seems A is not necessary.
upvoted 1 times
...
Alizade
1 year ago
Selected Answer: D
Facilitate the meeting so anyone can share their ideas and is heard during the session
upvoted 2 times
...
AmitBI
1 year ago
Selected Answer: A
Close call between Option A and D, But looking at option A, it seems discussing with team regarding RCA and then it will lead to possible causes and resolution to improve the project quality.SO option A covers all aspects including D
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: D
D. Facilitate the meeting so anyone can share their ideas and is heard during the session
upvoted 1 times
Sketchie
1 year ago
Aren't they already at a meeting? The PO made the suggestion at the meeting.
upvoted 1 times
...
...
Akhundzada
1 year, 1 month ago
Selected Answer: D
D. Facilitate the meeting so anyone can share their ideas and is heard during the session. In project management, it's important to involve the project team and gather their input when addressing quality issues. Facilitating a meeting where everyone can share their ideas helps ensure that all relevant perspectives are considered and that the team is engaged in identifying the root causes of the quality issues. This approach promotes collaboration and a sense of ownership among the team members. Once the root causes are identified, the team can work together to develop and implement appropriate solutions, which aligns with the project lead's responsibility for managing the project and its issues effectively.
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: D
It is important to listen to everyone, not just the PO.
upvoted 1 times
SteAle
1 year, 2 months ago
Changed my mind, it should be A, as D does not solve the problem. Plus A includes D.
upvoted 1 times
...
...
AbbasTaki
1 year, 3 months ago
Selected Answer: D
The project lead should facilitate the meeting so that everyone can share their ideas and be heard during the session. Option D is the most appropriate course of action in this scenario.
upvoted 1 times
...
suflam3
1 year, 4 months ago
Selected Answer: A
A makes sense. Answer D is part of A. D. Facilitate the meeting so anyone can share their ideas and is heard during the session. By doing A, PM is tabling product owner's recommendation to the team (which fits the bill that anyone can share their ideas and is heard during the session - Option D), but not necessarily deciding on PO's recommendation. After the discussion with the team, the PM will then implement the agreed-on solutions which is decided by the entire team.
upvoted 3 times
...
JMCCRAY
1 year, 4 months ago
Selected Answer: D
D. Facilitate the meeting so anyone can share their ideas and is heard during the session. In this situation, the best course of action for the project lead is to facilitate the meeting to ensure that everyone has the opportunity to share their ideas and that their contributions are heard. Root cause analysis (RCA) is an effective problem-solving technique used to identify the underlying cause(s) of an issue or problem. The project lead should encourage the team to work collaboratively to identify the root cause of the quality issues and to propose solutions to prevent the issue from recurring. By facilitating the meeting, the project lead can ensure that all team members are engaged, their ideas are considered, and that the team arrives at a consensus on how to move forward. This approach will increase the chances of finding an effective solution that the entire team supports and will ultimately lead to a more successful outcome for the project.
upvoted 1 times
...
mangostiffy
1 year, 5 months ago
I'll go with D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...