A large multi-year project requires highly skilled staff for successful deployment. The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun. However, there is a risk of staff turnover during the course of the project, which may have an impact on the delivery.
Which two actions should the project manager take to mitigate this risk? (Choose two.)
Adeshola1960
Highly Voted 2 years, 3 months agoDucwanosoft
Most Recent 5 days, 21 hours agoLucky_Cindy
1 year, 5 months agoFyrus
1 year, 6 months agovictory108
1 year, 7 months agoSteAle
1 year, 9 months agoAbbasTaki
1 year, 10 months agoRevZig67
2 years agoHung3102
2 years agoTrytrio
2 years, 1 month agoRiro2
2 years, 2 months agoKA90
2 years, 5 months agorajeshtk
2 years, 5 months agopmp_237student
2 years, 2 months agovuongchu09
7 months, 2 weeks ago