Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 361 discussion

Actual exam question from PMI's PMP
Question #: 361
Topic #: 1
[All PMP Questions]

A large multi-year project requires highly skilled staff for successful deployment. The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun. However, there is a risk of staff turnover during the course of the project, which may have an impact on the delivery.
Which two actions should the project manager take to mitigate this risk? (Choose two.)

  • A. Meet with management to discuss dividing the project into smaller projects.
  • B. Convince senior management to hire third-party staff.
  • C. Enhance the competencies of the project team through training, mentoring, and coaching.
  • D. Increase the trained staff to create back-up for resources.
  • E. Introduce a recognition program to motivate and reward resource performance.
Show Suggested Answer Hide Answer
Suggested Answer: CE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Adeshola1960
Highly Voted 1 year, 8 months ago
Selected Answer: CE
C. Enhance the competencies of the project team through training, mentoring, and coaching. Enhancing the competencies of the project team will help to ensure that the team has the skills and knowledge needed to deliver the project successfully. This will help to mitigate the risk of staff turnover as the team will be more capable of handling the project's complexities and challenges. E. Introduce a recognition program to motivate and reward resource performance. Recognition programs can help to retain staff by providing rewards and incentives for good performance. Additionally, it can also help to improve motivation and engagement among staff, which can help to mitigate the risk of staff turnover.
upvoted 5 times
...
Lucky_Cindy
Most Recent 10 months, 3 weeks ago
Selected Answer: CE
C&E are correct
upvoted 1 times
...
Fyrus
11 months, 1 week ago
Selected Answer: CD
I mean... C and D are pretty much complementary... E seems a good idea as well but if C is right, why should D be right too?
upvoted 1 times
...
victory108
1 year ago
Selected Answer: CD
C. Enhance the competencies of the project team through training, mentoring, and coaching D. Increase the trained staff to create back-up for resources
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: CE
I think that E will be more effective in addressing staff turnover
upvoted 2 times
...
AbbasTaki
1 year, 3 months ago
Selected Answer: CE
The two actions that the project manager should take to mitigate the risk of staff turnover are: C. Enhance the competencies of the project team through training, mentoring, and coaching. E. Introduce a recognition program to motivate and reward resource performance. These actions will help to ensure that the project team is highly skilled and motivated, which will reduce the likelihood of staff turnover.
upvoted 3 times
...
RevZig67
1 year, 5 months ago
Selected Answer: CD
These two actions can help mitigate the risk of staff turnover during the course of the project. By enhancing the competencies of the project team through training, mentoring, and coaching, the project manager can ensure that team members are more skilled and motivated to stay with the project. By increasing the trained staff to create back-up for resources, the project manager can ensure that there are enough resources to cover any unexpected turnover.
upvoted 1 times
...
Hung3102
1 year, 5 months ago
Agree C and E
upvoted 1 times
...
Trytrio
1 year, 6 months ago
Selected Answer: CE
C&E are my answers
upvoted 2 times
...
Riro2
1 year, 7 months ago
Selected Answer: DE
I will say D & E
upvoted 2 times
...
KA90
1 year, 10 months ago
Selected Answer: DE
I think D, E are correct
upvoted 3 times
...
rajeshtk
1 year, 10 months ago
why D is not correct?
upvoted 4 times
pmp_237student
1 year, 8 months ago
Increasing the trained staff will increase budget over-run
upvoted 5 times
vuongchu09
2 weeks, 5 days ago
Why C won't increase budget?
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...