exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 345 discussion

Actual exam question from PMI's PMP
Question #: 345
Topic #: 1
[All PMP Questions]

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer.
What guidance should the product manager provide to improve the requirement development?

  • A. Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.
  • B. Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.
  • C. Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.
  • D. Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
RomanPorcupine
2 weeks ago
Selected Answer: C
C is the most reasonable. I know lots of people mentioned PM cannot reprioritize the backlog in agile. That is correct. However, the question is asking what GUIDANCE the PM should PROVIDE, not what the PM should do.
upvoted 1 times
...
josephsafiran
11 months, 2 weeks ago
Selected Answer: C
The product manager should C. Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work. This approach ensures that the team is focusing on delivering value while also addressing complex requirements. It allows for incremental progress on the complex requirement, which can help manage risk and provide opportunities for learning and adjustment as the team gains more understanding of the requirement.
upvoted 1 times
...
Lucky_Cindy
1 year, 1 month ago
Selected Answer: C
C, MVP
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: C
C. Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work
upvoted 1 times
...
Digester
1 year, 7 months ago
C looks ok but it seems that the PM cannot prioritize the backlog in an agile environment. it’s so confusing that sometimes, the answer allows PM to prioritize the backlog sometimes it says it’s wrong if a PM prioritized the backlog.
upvoted 2 times
adingmaki
1 year, 2 months ago
It says reprioritize with the team. Including PO
upvoted 1 times
...
...
Alizade
1 year, 8 months ago
Selected Answer: C
The product manager should collaborate with the team to break down the complex requirement into smaller, manageable portions that can be incorporated into the product backlog. This approach allows the team to work on the complex requirement incrementally, delivering value to the customer and potentially making it easier to demonstrate progress. By reprioritizing the backlog and integrating portions of the complex work, the team can better manage the requirement development process. Options A, B, and D do not address the need to break down the complex requirement into manageable portions or to deliver value incrementally to the customer.
upvoted 3 times
...
Drogbadrog
1 year, 9 months ago
Prioritising of backlog is done by the product owner so i think its B
upvoted 1 times
...
Baj2023
1 year, 10 months ago
C. Never kick the issue downstream so A and B are incorrect. Also never run to client, sponsor or management as your 1st option so D is incorrect
upvoted 1 times
...
FlorinaP
1 year, 10 months ago
Selected Answer: B
Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project. making sure that the technical work is done is essential. it's like having proper infrastructure to be able to build on top of it.
upvoted 2 times
...
Adeshola1960
1 year, 11 months ago
Selected Answer: C
C. Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work. In this situation, the PRODUCT MANAGER should discuss the technical, complex requirement with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work. This approach will allow the team to focus on delivering the most important features and functionality to the customer while also addressing the complex requirement. The product manager should also work with the team to identify ways to deliver visual representations of the complex work to the customer, such as diagrams, flowcharts, or mock-ups. It is important not to lower the priority of the complex activity because it will increase the risk of finding issues later in the project and not to inform the customer that there will not be any deliverable due to the complexity involved in the requirement because it could create dissatisfaction with the product.
upvoted 2 times
Sketchie
1 year, 3 months ago
Thank you so much for highlighting the word "Product Manager". I totally missed it and had wondered why the correct answer was C
upvoted 1 times
...
...
TheAWSGuru
2 years ago
Selected Answer: B
B is the answer
upvoted 1 times
...
Balaraju
2 years, 1 month ago
Selected Answer: C
Sry, as mentioned, C is the right answer.
upvoted 2 times
...
Balaraju
2 years, 1 month ago
I think its B, as mentioned in option C, PM can not reprioritize backlogs.
upvoted 1 times
ChezQW
1 year, 1 month ago
I believe the backlog being referenced here is the sprint backlog not the product backlog.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago