Exam PMP topic 1 question 449 discussion

Actual exam question from PMI's PMP
Question #: 449
Topic #: 1
[All PMP Questions]

A project manager just started managing agile projects. The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD), their colleague's projects have had many difficulties. Sponsors keep asking for more features and the projects have yet to be completed.
What should the project manager do to avoid these issues?

  • A. Arrange meetings to ensure every necessary task to complete the project is included in the project management plan
  • B. Convince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed
  • C. Convince the product owner to approach the team and look for options to find a solution to the problem
  • D. Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months ago
Selected Answer: D
D. Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project
upvoted 2 times
...
Aish_
8 months, 2 weeks ago
Selected Answer: D
Building an agile project charter and setting clear expectations with key stakeholders will help define the project's objectives and scope from the outset. This will establish a common understanding of what is expected to be delivered, the project's goals, and the definition of done (DoD). This proactive approach can prevent scope creep and ensure that the project remains focused and aligned with stakeholder expectations.
upvoted 2 times
...
Hung1
1 year ago
Go with D
upvoted 2 times
...
PMPStudent
1 year, 4 months ago
Selected Answer: D
I think D is correct. Sponsors keep asking for more features. Option "B" does not fix the problem, team cannot find a solution to the problem. Even defining DOD would not help. DOD simply is just an acceptance criteria for the deliverable. Defining DOD will not stop the stakeholders from asking more. We need a project charter to define the project objectives and high level requirements.
upvoted 3 times
...
Franco11
1 year, 5 months ago
Selected Answer: C
I will go for C as the problem is lack of definition of done of the requirements and not lack of directions and vision. the it's the product owner responsibility
upvoted 1 times
lannt307
1 year, 5 months ago
I think D is correct. Because: The project manager realizes that due to the lack of a "clear definition of project objectives" and definition of done (DoD) -> So that I think need to build the agile project charter and set clear expectations for the project with key stakeholders in the meeting.
upvoted 6 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago