exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 189 discussion

Actual exam question from PMI's PMP
Question #: 189
Topic #: 1
[All PMP Questions]

An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.
Which approach should be used in this situation?

  • A. A flow-based approach starting with the smallest stories.
  • B. An iterative approach starting with the highest value epic.
  • C. A predictive approach with short phases.
  • D. An incremental approach with a minimum viable product (MVP).
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlekhyaT
Highly Voted 1 year, 10 months ago
sorry typo Answer is B. key words “ will be delivered when fixed price reached” . it means single delivery. “scope adjusted every iteration” means activities repeated until correct. This reflects “Reliability of the solution” not the speed to deliver the solution”. so its iterative approach
upvoted 11 times
...
Anssoo
Most Recent 3 days, 4 hours ago
Selected Answer: D
D is the correct answer. The question is MVP concept.
upvoted 1 times
...
ductrinh
1 week, 2 days ago
Selected Answer: B
sell the highest first >>
upvoted 1 times
ductrinh
1 week, 2 days ago
example : you have 3 apples which price are 10$, 5$ and 1$. which one do you like to sell first ?
upvoted 1 times
...
...
krispara
3 months ago
Selected Answer: B
An iterative approach ensures that work is delivered in iterations, and prioritizing the highest-value epic aligns with delivering the most critical business outcomes first.
upvoted 1 times
...
kavikris
4 months ago
Selected Answer: D
If iterative is followed its a risk as the project may be halted when the price is reached and teh iteration may not be useful, instead incremental approach delivering MVP will be the speedy option and can guarantee some minimal features if the project gets stopped, so the idea is to deliver fast not deliver by improving based on feedback
upvoted 2 times
...
Amirov
5 months ago
Selected Answer: B
I choose B
upvoted 1 times
...
6114c29
5 months, 1 week ago
Selected Answer: B
B. An iterative approach starting with the highest value epic.
upvoted 1 times
...
Paramak
7 months, 2 weeks ago
Selected Answer: D
D makes sense
upvoted 1 times
...
tonybuivannghia
8 months, 2 weeks ago
Selected Answer: B
Because we need to release in each iteration base on the cryptocurrency price. so B is correct
upvoted 1 times
...
KennyMuffins
1 year, 1 month ago
Selected Answer: D
Iterative - > Overall solution, then refine areas that need improvement, project might be halted before overall solution can be produced. Incremental -> Building and releasing one usable feature at a time, even when project is halted at any point, client has a workable product.
upvoted 2 times
...
josephsafiran
1 year, 2 months ago
Selected Answer: D
The project manager should use **an incremental approach with a minimum viable product (MVP)** (Option D). This approach allows the team to deliver value early and often, with each increment adding to the functionality of the product. Given the volatility of cryptocurrency, this approach allows for flexibility in adjusting the scope based on the value of the cryptocurrency at the end of each iteration. It also ensures that the project can be halted when the agreed price is reached, while still delivering a functional product to the client. This approach aligns well with Agile principles, which emphasize customer satisfaction through continuous delivery of valuable software.
upvoted 1 times
...
Only12go
1 year, 5 months ago
Selected Answer: B
Given the unique situation where the scope is adjusted based on the value of the cryptocurrency at the end of every iteration, the best approach would involve delivering maximum value as early as possible, ensuring that the client gets the most essential features before the agreed price is reached.
upvoted 2 times
...
Fyrus
1 year, 6 months ago
Selected Answer: D
D, since B may give you a huge nice Epic, concluded in an incomplete project. Let's think: The project: Online store The Epic: Make all the pages for Create, Read, Delete and Update products in the store and the user panel to add items on the cart and pay. 2% of the total price payed will be cash-backed in points to give the users discounts Story that is not in the epic: Login system with "I forgot my password" It seems stupid to put it like that but we should first point to the MVP and then think of adding epics that may be so big that may consume the whole budget
upvoted 1 times
...
Goku_PMP
1 year, 7 months ago
Selected Answer: B
As the delivery is based on volatility of crypto, the best part is to pick story which will give high value for customer and release until the agreed value of cryptocurrency is reached. This is actually WIN WIN situation for both parties.
upvoted 4 times
...
DodoTommy
1 year, 8 months ago
D They will halt (stop) the project when price is reached and not deliver when price is reached. Definitely the answer is D
upvoted 1 times
...
SteAle
1 year, 9 months ago
Selected Answer: D
An iterative approach is useful if the focus is on the correctness of the solution. The team might run out of budget without being able to achieve any working results. Whereas, an incremental approach promotes providing value to the customer as early as possible. If we combine it with MVP, the chances of getting something valuable & working before the budget runs out are higher.
upvoted 2 times
...
victory108
1 year, 9 months ago
Selected Answer: B
B. An iterative approach starting with the highest value epic
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago