A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.
What should the project manager do to support the team?
zul_n
Highly Voted 1 year, 11 months agofragar65
Most Recent 1 month, 2 weeks agoAmirov
1 month, 2 weeks agohoomz
9 months, 1 week agoDavard
10 months, 1 week agoCommonNickname
10 months, 2 weeks agoDavard
10 months, 2 weeks agoUncle_Lucifer
1 year, 1 month agoUncle_Lucifer
1 year agoxpz
1 year, 2 months agosambeth
1 year, 2 months agobabasoo
1 year, 2 months agobug_bloke
1 year, 3 months agovictory108
1 year, 6 months agoHung1
1 year, 7 months agoDinesh1987
1 year, 8 months agogspace
1 year, 9 months agohary61
1 year, 10 months agoalt_coffey
1 year, 9 months ago