A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan.
The project manager starts to present the budget but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
JYKL88
Highly Voted 1 year, 4 months agocwilson91
1 year, 2 months agoDavid983
11 months, 2 weeks agoKim222
Most Recent 3 weeks agoKennyMuffins
7 months, 3 weeks agojosephsafiran
7 months, 3 weeks agoxcjxcj
9 months, 3 weeks ago[Removed]
10 months, 1 week agovictory108
1 year agoPaulPMP
1 year, 6 months agoPMPStudent
1 year, 9 months agoFranco11
1 year, 11 months ago