Exam PMP topic 1 question 420 discussion

Actual exam question from PMI's PMP
Question #: 420
Topic #: 1
[All PMP Questions]

A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points.
Which team is performing better?

  • A. Team A as they have calculated fewer story points than team B
  • B. Team B as they have calculated more story points than team A
  • C. The team that completes the most stones selected from the sprint backlog
  • D. The team with the least amount of defects in their deliverables
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PhongDang_PM
1 week, 3 days ago
Selected Answer: C
I select C because the most important for Agile team is to complete the work in the selected sprint backlog. Option C, if they have few defects but the completed amount is smaller than plan, it does not make sense.
upvoted 1 times
...
xcjxcj
10 months, 4 weeks ago
Selected Answer: C
C better. If D is correct, please explain below: team A done 100 tasks with 100 defects, team B done 125 tasks with 101 defects, team win.
upvoted 2 times
...
cb4a6c4
11 months, 1 week ago
Confused between C and D If C - There is no guarantee of value delivered. Teams would have worked on less impactful tasks or compromised quality. if D - Chances that low value features were delivered. Any thougts?
upvoted 1 times
...
Satyabrata_Paul
1 year ago
if team A completes 10 story points with no defects and another team B completes 90 story points with 1 defect, then who is performing better? Will you go with A?
upvoted 2 times
...
kevzzz
1 year, 3 months ago
Selected Answer: D
Little to no rework required.
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: D
Typical mistake #1. Velocity is unique for each team, mostly because of the team’s own definition of story points. So velocity is not useful as a comparison metric for team performance.
upvoted 3 times
...
Yuxiao
1 year, 5 months ago
should be C. See how many milestone you completed
upvoted 1 times
...
PMPStudent
1 year, 11 months ago
Selected Answer: D
D sounds better
upvoted 3 times
...
Franco11
2 years ago
What do u think guys about this question? the outperforming team is the one who has completed more story points.
upvoted 2 times
PMPStudent
1 year, 11 months ago
Every team has different sizing specifications, you cannot judge a team's performance on the basis of the story points. Sizing really does not matter in terms of performance.
upvoted 6 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...