A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
rajeshtk
Highly Voted 1 year, 10 months agoKim222
3 weeks agoAmitBI
1 year agoKim222
Most Recent 3 weeks agotonybuivannghia
2 months agoc8ee0e6
2 months agoBruce_Liu
8 months, 1 week agojosephsafiran
8 months, 2 weeks agohuynq185
10 months, 2 weeks agoLucky_Cindy
10 months, 3 weeks ago[Removed]
10 months, 3 weeks agoOnly12go
11 months, 1 week agokevzzz
11 months, 1 week agovictory108
1 year, 1 month agoAsakthi
1 year, 1 month agoOrochi
1 year, 3 months agosuflam3
1 year, 4 months agoJMCCRAY
1 year, 4 months agoGoku_PMP
1 year, 1 month agozayn_1983
1 year agosnagile
1 year, 4 months ago