Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 303 discussion

Actual exam question from PMI's PMP
Question #: 303
Topic #: 1
[All PMP Questions]

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.
What should the project manager do?

  • A. Ensure the client representative is involved in the estimation.
  • B. Ensure that a 20% contingency is included in the estimation.
  • C. Review the completion costs of similar projects.
  • D. Review the lessons learned from similar projects.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Angra
1 month, 2 weeks ago
Selected Answer: C
The answer is definitely C. As the definition of PMP. "Lessons learned" is a work review recorded by those who participated in the "project" work after the work is completed. "lessons learned" mainly records the reasons for the success of the work and the reasons for the failure. "History information" is also called history records. "History information" records quantitative data after the completion of various project work, including the actual construction period, actual cost used, and the actual number of resources used after the work is completed. If you want to choose D Then the answer should be described like this "Review the history information from similar projects."
upvoted 1 times
...
23169fd
2 months ago
Selected Answer: C
analogous estimating techniques
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
I think we can gain insight into the project by reviewing the lessons learned.
upvoted 1 times
...
nealmukundan
3 months, 2 weeks ago
Selected Answer: D
CHATGPT answer is D review lesson learned
upvoted 1 times
...
akashushi007
5 months ago
Selected Answer: C
C. Review the completion costs of similar projects. This option is the most appropriate because: Historical Data: Reviewing the completion costs of similar projects provides concrete data that can be used to estimate costs more accurately. This data can help predict the resources, time, and budget needed for the new project based on past experiences. Benchmarking: Similar projects serve as benchmarks, allowing the project manager to make more realistic and evidence-based cost estimates.
upvoted 1 times
...
52d1fe0
6 months, 4 weeks ago
Review the lessons learned from similar projects.
upvoted 1 times
...
psemdel
7 months, 3 weeks ago
A very good question, I would like to have the answer in real life :). I think C, the question is about costs, how should the lesson learned help giving a price?
upvoted 1 times
...
Deeski
11 months, 1 week ago
Selected Answer: D
One method to enhance budget estimating is to review budget-related lessons learned from similar projects
upvoted 3 times
...
Biggy88
1 year ago
Selected Answer: A
Ensure the client representative is involved in the estimation: In agile projects, it's essential to involve the client or customer representative in the estimation process. They can provide valuable input and insights into their priorities, requirements, and expectations, which can help make the estimation more accurate. Agile values customer collaboration, so their involvement is crucial.Option A) because it aligns with the agile principles of customer collaboration and responding to change. Therefore, Option A is the most important consideration in this context
upvoted 2 times
...
Lucky_Cindy
1 year ago
Selected Answer: D
D review lesson learned
upvoted 1 times
...
Only12go
1 year, 1 month ago
Selected Answer: C
C. Review the completion costs of similar projects. To provide a cost estimation for the business case in an agile project, it's helpful to review the completion costs of similar projects or reference historical data from similar agile projects. This can provide valuable insights into the expected costs based on past experiences. While involving the client representative, including contingency, and reviewing lessons learned are important aspects of project planning, reviewing completion costs from similar projects is the most direct way to estimate costs for the business case.
upvoted 1 times
...
RestlessMonkey
1 year, 1 month ago
Selected Answer: A
Maybe I am overthinking this, but I believe the correct answer is A. It is my understanding that Agile favours bottom-up estimating ahead of analogous. Additionally, you cannot estimate costs before understanding the scope of the project, the customer representative will be able to provide an understanding of the features that need to be developed or prioritized, based on this information you can then go ahead and estimate costs.
upvoted 4 times
...
adingmaki
1 year, 1 month ago
D. Review the lessons learned which includes the cost estimation.
upvoted 1 times
...
Fyrus
1 year, 2 months ago
Selected Answer: C
C relies on empiricism to (help to) solve the problem of cost estimation in a agile project
upvoted 1 times
...
Parithi
1 year, 2 months ago
D. Review the lessons learned from similar projects.
upvoted 1 times
...
kevzzz
1 year, 2 months ago
Selected Answer: D
Collect and document the lessons learned and feedback from the sources you identified. You can use surveys, interviews, focus groups, workshops, or questionnaires to ask specific and relevant questions that can help you identify the root causes, impacts, and solutions of your cost problems. Examples of questions you may ask include: what were the main sources of cost overruns and variances in your project? How did you measure and report your cost performance and progress? How did you handle and mitigate the cost issues and changes? What were the best practices and success factors for cost control in your project? What were the challenges and risks for cost control in your project? And what would you do differently or improve for cost control in your future projects?
upvoted 3 times
...
psvexam
1 year, 2 months ago
Ans: C. What is the guarantee that lessons learnt will have all cost details of a project. So C is better suited than D. Reviewing completion costs of other projects may be more relevant to determine high level estimates.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...