Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 18 discussion

Actual exam question from PMI's PMP
Question #: 18
Topic #: 1
[All PMP Questions]

A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?

  • A. Fast track the project
  • B. Adjust the budget
  • C. Introduce a float
  • D. Adjust the project time line
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
joesatriani
Highly Voted 2 years, 1 month ago
Answer is A. SPI = EV/ PV. EV(US$500,000) / PV(US$550,000) = 0.9 So current SPI is < 1. It means behind schedule.
upvoted 34 times
...
Tuanit
Highly Voted 1 year, 1 month ago
Selected Answer: A
Project is behind schedule so this question considers techniques to compress project schedule which is either Fast Tracking (increases risks) or Crashing (increases cost). D could be an option, however timeline adjustment must go through Change Control. Another point, the question mentions "critical project", it might (not explicitly though) mean a tight deadline. There is no mentioning or factors not to use Fast Track.
upvoted 9 times
...
Deepakuc
Most Recent 1 week, 4 days ago
Option A
upvoted 1 times
...
Aish_
2 months ago
Selected Answer: A
Voting for Fast Tracking. If the project is almost completed, and there is a schedule variance (earned value is less than planned value) at the end of Sprint 3, fast tracking becomes a suitable option to expedite the remaining tasks and bring the project back on track Option D (Adjust the project timeline) could still be valid in certain situations, especially if the project is not close to completion or if fast tracking is not feasible due to resource constraints or risks associated with overlapping tasks. However, since the project is almost over, adjusting the timeline may not provide sufficient time to recover from the schedule variance.
upvoted 4 times
...
Karan1102
7 months, 1 week ago
D. Adjusting the project timeline is the most suitable action. Since the earned value (EV) is less than the planned value (PV), it means that the project is behind schedule at the end of sprint three. In this case, the project manager should consider adjusting the project timeline by extending the remaining sprint(s) or adding additional sprints to account for the work that is behind schedule. This will help ensure that the project can be completed within the adjusted timeline.
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: A
A. Fast track the project
upvoted 1 times
...
Mamoonpk
1 year ago
Selected Answer: A
Fast tracking
upvoted 1 times
...
adingmaki
1 year, 1 month ago
I'm wrong. It's supposed to be fast track. We can fast track projects in software agile. Because the impact of the risk is not that high in software environments. It's easily fixed.
upvoted 2 times
...
adingmaki
1 year, 1 month ago
https://www.pmi.org/learning/library/scheduling-resource-leveling-project-progression-8006 D. Level your resources. Fast tracking has a lot of risks. It's a critical software development
upvoted 1 times
...
Alphy07
1 year, 2 months ago
A is correct
upvoted 1 times
...
kayyaly
1 year, 3 months ago
Selected Answer: A
A is the correct answer, SPI < 1
upvoted 1 times
...
ziyaetuk
1 year, 4 months ago
Selected Answer: D
In this situation, the best option would likely be D. Adjust the project timeline. This could involve re-estimating the remaining tasks, potentially extending the timeline for the final sprint, or adjusting the schedule for specific tasks. Option A, fast-tracking the project, could lead to increased risk and might not be feasible depending on the nature of the work remaining. Option B, adjusting the budget, doesn't directly address the issue, which is a schedule variance, not a cost variance. Option C, introducing a float, refers to schedule flexibility that is typically built in at the planning stage and might not be applicable or sufficient in this situation.
upvoted 1 times
...
ompk
1 year, 4 months ago
ChatGpt says Option B
upvoted 1 times
djgdgaf
8 months, 4 weeks ago
I got D with chat gpt because of the increased risks and it may lead to rework if tasks are rushed. However, I agree with the majority that A is the correct.
upvoted 2 times
...
...
SteAle
1 year, 4 months ago
Answer A. I don't think it's best practice to keep adjusting the baseline every time there is a delay on a project.
upvoted 2 times
...
victory108
1 year, 6 months ago
Selected Answer: A
A. Fast track the project
upvoted 1 times
...
MaxInsane
1 year, 7 months ago
VOTED A SPI<1. This implies it's behind schedule. Fast tracking and crashing are ways to correct this. Among the options A feels like the most appropriate.
upvoted 2 times
...
BenPappoe
1 year, 7 months ago
Selected Answer: B
Voted B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...