A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?
joesatriani
Highly Voted 2 years, 1 month agoTuanit
Highly Voted 1 year, 1 month agoDeepakuc
Most Recent 1 week, 4 days agoAish_
2 months agoKaran1102
7 months, 1 week agoBuviD
10 months, 3 weeks agoMamoonpk
1 year agoadingmaki
1 year, 1 month agoadingmaki
1 year, 1 month agoAlphy07
1 year, 2 months agokayyaly
1 year, 3 months agoziyaetuk
1 year, 4 months agoompk
1 year, 4 months agodjgdgaf
8 months, 4 weeks agoSteAle
1 year, 4 months agovictory108
1 year, 6 months agoMaxInsane
1 year, 7 months agoBenPappoe
1 year, 7 months ago