The deliverables of a project have been completed. However, the stakeholders did not approve the deliverables, because they did not cover the needs of the business. Which actions should the project manager have taken to avoid this situation?
A.
Defined the project management plan and ensured it met the project objectives and business needs.
B.
Ensured that the stakeholders participated in the daily meetings to confirm that the project was developing correctly.
C.
Provided and explained the sprint backlog at the beginning of the project to the stakeholders and project team.
D.
Requested that the team change the frequency of the deliverables in the development phase to obtain earlier feedback.
Stakeholders don't usually join daily team meetings, also backlog and stories are not usually developed earlier in the planning
upvoted 2 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Macko1
3 weeks, 4 days agoLucky_Cindy
1 year agovictory108
1 year, 3 months agoSteAle
1 year, 4 months agoHung1
1 year, 7 months agoAlphasham
2 years, 1 month agoKA90
2 years ago