Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 306 discussion

Actual exam question from PMI's PMP
Question #: 306
Topic #: 1
[All PMP Questions]

The deliverables of a project have been completed. However, the stakeholders did not approve the deliverables, because they did not cover the needs of the business.
Which actions should the project manager have taken to avoid this situation?

  • A. Defined the project management plan and ensured it met the project objectives and business needs.
  • B. Ensured that the stakeholders participated in the daily meetings to confirm that the project was developing correctly.
  • C. Provided and explained the sprint backlog at the beginning of the project to the stakeholders and project team.
  • D. Requested that the team change the frequency of the deliverables in the development phase to obtain earlier feedback.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Macko1
3 weeks, 4 days ago
Selected Answer: D
Faster feedback loops
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: A
A. Defined the project management plan and ensured it met the project objectives and business needs
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: A
A. Defined the project management plan and ensured it met the project objectives and business needs
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
A solid project management plan ensures that the project will be executed to meet the objectives and needs.
upvoted 1 times
...
Hung1
1 year, 7 months ago
Question does not mention using agile, A is answer.
upvoted 2 times
...
Alphasham
2 years, 1 month ago
Why not D or a 2nd option C may be?
upvoted 1 times
KA90
2 years ago
Stakeholders don't usually join daily team meetings, also backlog and stories are not usually developed earlier in the planning
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...