A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials.
What should the project manager do next?
ea4e1f8
3 weeks, 1 day agoDavidTri
2 months, 2 weeks agoBruce_Liu
6 months, 2 weeks agojosephsafiran
7 months, 3 weeks agoOnly12go
11 months, 1 week agoadingmaki
11 months, 2 weeks agoDavid983
11 months, 2 weeks agoAish_
1 year, 1 month agoAish_
1 year, 1 month agoSynikalDemon
1 year, 2 months agoAbbasTaki
1 year, 3 months agoEC123
1 year, 3 months agoadingmaki
11 months, 2 weeks agoFaozi
1 year, 3 months agoFiona1212
1 year, 4 months agoemelba
1 year, 4 months agoRevZig67
1 year, 5 months agoJYKL88
1 year, 5 months agoHung3102
1 year, 5 months ago