Question #: 323
Topic #: 1
[All PMP Questions]

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.
How should the project manager handle this issue?

  • A. Support a voting exercise so all team members can express their opinion and the reason behind their vote.
  • B. Support the project sponsor so the decision is made top-down and the team follows the provided direction.
  • C. Support the product owner so only items with high business value are included in the next sprint.
  • D. Support the project team so technical debt and infrastructure dependencies are included in the next sprint.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Paramak
1 month ago
Selected Answer: A
Option A aligns with Agile principles, encouraging collaboration and collective decision-making within the team.
upvoted 1 times
...
MsPigeon
1 month, 3 weeks ago
Selected Answer: A
A. The team is also empowered to provide feedback and opinion on their expert areas - development. Product owner might not understand the risk of technical debt and infra readiness/dependencies. There is also no story on technical debt and infra dependency.
upvoted 1 times
...
mrwriting
5 months, 2 weeks ago
Selected Answer: A
What happens if high-value items depend on technical? So priority bases on high risk/high value first.
upvoted 1 times
...
mdkhassan
5 months, 4 weeks ago
Selected Answer: A
The voting exercise allows the project team to collectively prioritize the items, taking into account both the business value and the technical debt and infrastructure dependencies. Through this exercise, the team can reach a consensus on how to balance the priorities and make an informed decision that considers both the short-term business value and the long-term technical stability of the product.
upvoted 1 times
...
[Removed]
6 months, 4 weeks ago
Selected Answer: A
A - What will happen with the technical debt when you ignore it?
upvoted 1 times
...
xcjxcj
8 months, 2 weeks ago
Selected Answer: C
Vote will kill PO decision. In agile, PO is in charge backlog priority.
upvoted 2 times
...
LeoChu
10 months ago
Selected Answer: A
Should be A, there is no story for technical debt and infrastructure dependencies.
upvoted 2 times
...
Lucky_Cindy
11 months ago
Selected Answer: C
Value-driven is the ke
upvoted 2 times
...
Tuanit
11 months, 2 weeks ago
Selected Answer: A
I choose A
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Support a voting exercise so all team members can express their opinion and the reason behind their vote
upvoted 1 times
...
Orochi
1 year, 3 months ago
C Value-driven is the key. Prioritization should not be confirmed by voting......Furthermore, the cost to achieve should be considered already before determine the business value
upvoted 1 times
...
Hung3102
1 year, 5 months ago
In Agile, the project manager should encourage collaboration and communication between the product owner and the project team to find a mutually acceptable solution. Based on the given scenario, the project manager should handle this issue by facilitating a discussion to balance technical debt and infrastructure dependencies with items of high business value. Therefore, option A is the most appropriate choice. Supporting a voting exercise where all team members express their opinions and the reason behind their vote can help the team find a compromise and identify items that provide both business value and address technical debt and infrastructure dependencies. The project manager should encourage the team to find a solution that meets both the product owner's and project team's concerns.
upvoted 2 times
...
emelba
1 year, 6 months ago
It's all about value here, son C works for me
upvoted 1 times
...
Trytrio
1 year, 6 months ago
Selected Answer: A
I would say A
upvoted 1 times
...
scrum888
1 year, 7 months ago
Option A. PMBOK 6 Pg. 144: Voting is a collective decision-making technique and an assessment process having multiple alternatives with an expected outcome in the form of future actions. These techniques can be used to generate, classify, and prioritize product requirements.
upvoted 4 times
...
Baj2023
1 year, 7 months ago
Selected Answer: C
The product owner is responsible for the prioritization of the product backlog and ensuring the team understands their value to the business
upvoted 3 times
...
FlorinaP
1 year, 7 months ago
Selected Answer: A
there should be a mechanism through which the team can add technical debts to the backlog and get proper prioritization from product owner. than the technical debts will get their own business value and get into the mix for prioritization
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...