Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 179 discussion

Actual exam question from PMI's PMP
Question #: 179
Topic #: 1
[All PMP Questions]

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?

  • A. Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.
  • B. Implement a scrum risk retrospective to analyze the risks at the end of the project.
  • C. Assign an agile risk manager to better understand and track the project risks.
  • D. Evaluate the risks constantly and reprioritize work as the project progresses.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tonybuivannghia
2 months ago
Selected Answer: D
High risk, high value
upvoted 1 times
...
SerMak
11 months ago
Selected Answer: D
D is correct. There is no such thing as agile risk matrix
upvoted 2 times
...
Lucky_Cindy
11 months, 2 weeks ago
Selected Answer: D
D is better fit
upvoted 1 times
...
Tuanit
11 months, 2 weeks ago
Selected Answer: D
I think D is better than A as it emphasizes constantly addressing risk & prioritize work
upvoted 1 times
...
BakM
11 months, 3 weeks ago
Selected Answer: D
both A and D are correct, but D is more correct. D has elements of constant evaluation of risk and reprioritization
upvoted 1 times
...
adingmaki
1 year ago
For disciplined agile, prioritize work based on risk for early mitigation, it's D.
upvoted 1 times
...
OruMary
1 year, 1 month ago
Is there anything like an agile risk Matrix? D is the answer.
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: D
I would go with D, as the risks should be constantly evaluated and addressed
upvoted 2 times
...
ElshRote
1 year, 3 months ago
Abd, yes, there is risk matrix in agile, but while A is what you do at the beginning of a project, D is what you do in this case, even as the project progresses.
upvoted 2 times
...
Neil20
1 year, 3 months ago
Selected Answer: D
D is correct
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: D
D. Evaluate the risks constantly and reprioritize work as the project progresses
upvoted 1 times
...
TBT_1
1 year, 3 months ago
Selected Answer: D
Managing risks is a continuous process
upvoted 1 times
...
Hung3102
1 year, 6 months ago
Ok D is answer. Option A (Developing an agile risk matrix) may be helpful, but it is not specific to an agile approach and may not be suitable for managing risks in an innovative project
upvoted 3 times
...
Ade1981
1 year, 9 months ago
I'll take D. It's Agile and there is no risk matrix. But regular evaluation seem closer to what is done in Agile
upvoted 2 times
...
arnibert
1 year, 9 months ago
Selected Answer: A
Agile let's you decide how much risk management you need and when - based on the nature of the project. No general requirement or need for a special matrix here (also this term does not exist I believe).
upvoted 2 times
leo_gold
1 year, 9 months ago
Risk Matrix in Agile!! I don't think there is a such thing.
upvoted 3 times
...
...
Pass_Exams100
1 year, 9 months ago
I think that's because agile method doesn't have a specific item called risk matrix.
upvoted 1 times
...
rajeshtk
1 year, 9 months ago
"A" is the right answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...