Question #: 555
Topic #: 1
[All PMP Questions]

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three.)

  • A. A team member talking about a user story that is not on the Scrum board
  • B. A team member talking about a user story that is on the Scrum board
  • C. A technology that blocks agile capabilities
  • D. A lack of team empowerment and an inability to self-organize
  • E. A review of the backlog at daily standup meetings
Show Suggested Answer Hide Answer
Suggested Answer: ACD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ljz
1 month, 2 weeks ago
Selected Answer: ACD
talking about user story that is on the scrum board and reviewing product backlog during scrum meeting is expected
upvoted 1 times
...
Jordarlu
2 months, 1 week ago
Selected Answer: ACD
I also vote for A, C, and D the reason for A is if a user story is mentioned not on the board and mentioned by the team member, that may imply an issue or dependancy to the current Sprint and has not been identified yet until now. Since the question was asking what scenarios are 'problems', I think PM should be pay attention to this option A. I think D is not a problem as reviewing the backlog although it is not best practice ,,but not really a problem to PM
upvoted 1 times
...
Kim222
7 months, 2 weeks ago
Selected Answer: ACD
This is ACD
upvoted 1 times
...
tonybuivannghia
8 months, 4 weeks ago
Selected Answer: CDE
I think A isn’t correct
upvoted 1 times
...
Only12go
1 year, 5 months ago
Selected Answer: ACD
A. A team member talking about a user story that is not on the Scrum board C. A technology that blocks agile capabilities D. A lack of team empowerment and an inability to self-organize
upvoted 3 times
...
prokat_mashin_na_vicecity
1 year, 6 months ago
Selected Answer: ACD
https://www.examtopics.com/discussions/pmi/view/52737-exam-pmp-topic-1-question-1787-discussion/
upvoted 1 times
...
victory108
1 year, 7 months ago
Selected Answer: CDE
C. A technology that blocks agile capabilities D. A lack of team empowerment and an inability to self-organize E. A review of the backlog at daily standup meetings
upvoted 1 times
...
Aish_
1 year, 8 months ago
Selected Answer: ACD
Reviewing the backlog during the Daily Scrum is not typically a problem, as long as the focus remains on the current sprint's commitments and progress. It's an opportunity to discuss the work planned for the sprint and any adjustments needed.
upvoted 1 times
...
RevZig67
2 years ago
Selected Answer: ACD
ACD is correct
upvoted 1 times
...
Hung3102
2 years ago
ACD are answers
upvoted 2 times
...
Ragaa
2 years, 2 months ago
Given answer is RIGHT..
upvoted 1 times
...
PMPStudent
2 years, 4 months ago
Selected Answer: CDE
I guess CDE is the correct answer.
upvoted 1 times
...
Franco11
2 years, 5 months ago
Selected Answer: CDE
Gonna go with CDE
upvoted 2 times
...
rajeshtk
2 years, 6 months ago
Isn't it CDE is the correct answer? A story on the board and not on the board why should be an impediment?
upvoted 2 times
Bobbie30
2 years, 4 months ago
My thoughts exactly!
upvoted 1 times
...
AstridN
1 year, 9 months ago
Maybe focus issue..
upvoted 1 times
...
Jamrock
1 year, 8 months ago
The question is "What is an impediment (problem)?"
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago