Actual exam question from PMI's PMP
Question #: 3
Topic #: 1
[All PMP Questions]

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.
What should the project manager do?

  • A. Include the customer in daily project activities to gain the required guidance
  • B. Plan ahead and define the best way to review the deliverables with the customer
  • C. Request the customer to clarify all requirements at the start of each iteration
  • D. Ask the customer to review the deliverables in each iteration based on their availability
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
3 days, 8 hours ago
Selected Answer: B
The right answer is B, the project manager needs to plan ahead to see when the client will best be available to review the feature changes, this way he/ she is able to gain timely feedback and avoid any cope creep that may result in the delay of execution of the project
upvoted 1 times
...
Gracemade
1 month ago
Selected Answer: B
Correct answer is B - Rather than reacting to the customer's absence, the project manager should proactively define a structured review process that aligns with the customer’s availability. Option D is reactive rather than proactive and could still result in delays.
upvoted 1 times
...
engamin
1 month, 3 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
FauziYusmin
2 months, 4 weeks ago
Selected Answer: D
The project manager needs to work proactively to ensure that customer feedback is received regularly and in a timely manner.
upvoted 1 times
...
ttkong168
3 months, 3 weeks ago
Selected Answer: D
B looks more like predictive. In Agile, planning should be throughout project and customer to review the deliverables in each iteration, hence D.
upvoted 1 times
...
MalikSaab
3 months, 4 weeks ago
Selected Answer: D
PM needs to make sure the deliverables are reviewed by client based on their availability
upvoted 1 times
...
crypto_dreams_medellin
4 months, 3 weeks ago
the customer has a tight schedule, he is very busy. The PM will have to work around the customer's schedule in order to go over the deliverables in a timely manner. He has to make the appointment happen with the customer if its going to happen, never give away your work.
upvoted 1 times
...
crypto_dreams_medellin
4 months, 4 weeks ago
B is the best answer, second is D.....We want closest to the correct answer.
upvoted 1 times
...
Pragati06
6 months, 2 weeks ago
Answer is B.PM need better planning ahead and improved communication channel
upvoted 1 times
...
Taha1981
6 months, 2 weeks ago
answer B
upvoted 1 times
...
Aditech
11 months, 3 weeks ago
(B) The project manager should communicate with the customer to establish a more reliable review schedule and consider alternative ways to gather feedback, such as virtual reviews or designated representatives. Adigun.
upvoted 3 times
...
berouz
11 months, 3 weeks ago
B. Because you have to plan ahead, project cant be delay and you have to define best way communicate with customer.
upvoted 3 times
...
09e9f80
1 year ago
B. Plan Ahead
upvoted 1 times
...
BuviD
1 year, 2 months ago
Selected Answer: B
B. Plan ahead and define the best way to review the deliverables with the customer
upvoted 2 times
...
khloreeen
1 year, 3 months ago
If you choose D there’ll be delay in delivery, so it’s B for me
upvoted 1 times
...
Mamoonpk
1 year, 4 months ago
D as it provides flexibility to customer as agile mindset
upvoted 1 times
...
Akintayo
1 year, 5 months ago
Selected Answer: B
answer is B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago