A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.
What should the project manager do?
Princessviv96
3 days, 8 hours agoGracemade
1 month agoengamin
1 month, 3 weeks agoFauziYusmin
2 months, 4 weeks agottkong168
3 months, 3 weeks agoMalikSaab
3 months, 4 weeks agocrypto_dreams_medellin
4 months, 3 weeks agocrypto_dreams_medellin
4 months, 4 weeks agoPragati06
6 months, 2 weeks agoTaha1981
6 months, 2 weeks agoAditech
11 months, 3 weeks agoberouz
11 months, 3 weeks ago09e9f80
1 year agoBuviD
1 year, 2 months agokhloreeen
1 year, 3 months agoMamoonpk
1 year, 4 months agoAkintayo
1 year, 5 months ago