Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 3 discussion

Actual exam question from PMI's PMP
Question #: 3
Topic #: 1
[All PMP Questions]

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.
What should the project manager do?

  • A. Include the customer in daily project activities to gain the required guidance
  • B. Plan ahead and define the best way to review the deliverables with the customer
  • C. Request the customer to clarify all requirements at the start of each iteration
  • D. Ask the customer to review the deliverables in each iteration based on their availability
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
crypto_dreams_medellin
2 weeks, 1 day ago
the customer has a tight schedule, he is very busy. The PM will have to work around the customer's schedule in order to go over the deliverables in a timely manner. He has to make the appointment happen with the customer if its going to happen, never give away your work.
upvoted 1 times
...
crypto_dreams_medellin
2 weeks, 5 days ago
B is the best answer, second is D.....We want closest to the correct answer.
upvoted 1 times
...
Pragati06
2 months ago
Answer is B.PM need better planning ahead and improved communication channel
upvoted 1 times
...
Taha1981
2 months, 1 week ago
answer B
upvoted 1 times
...
Aditech
7 months, 2 weeks ago
(B) The project manager should communicate with the customer to establish a more reliable review schedule and consider alternative ways to gather feedback, such as virtual reviews or designated representatives. Adigun.
upvoted 3 times
...
berouz
7 months, 2 weeks ago
B. Because you have to plan ahead, project cant be delay and you have to define best way communicate with customer.
upvoted 3 times
...
09e9f80
8 months, 3 weeks ago
B. Plan Ahead
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: B
B. Plan ahead and define the best way to review the deliverables with the customer
upvoted 2 times
...
khloreeen
11 months, 2 weeks ago
If you choose D there’ll be delay in delivery, so it’s B for me
upvoted 1 times
...
Mamoonpk
1 year ago
D as it provides flexibility to customer as agile mindset
upvoted 1 times
...
Akintayo
1 year ago
Selected Answer: B
answer is B
upvoted 1 times
...
Ravi4french
1 year, 1 month ago
Selected Answer: D
D. Ask the customer to review the deliverables in each iteration based on their availability
upvoted 1 times
...
Kojodade
1 year, 2 months ago
Selected Answer: B
VOTE B
upvoted 1 times
...
lan_think
1 year, 2 months ago
Selected Answer: B
vote B
upvoted 1 times
...
rockylee
1 year, 2 months ago
Selected Answer: B
Vote B
upvoted 1 times
...
Trollem
1 year, 3 months ago
Selected Answer: B
Vote B
upvoted 1 times
...
sapku
1 year, 3 months ago
B proactive planning to define the best way to review deliverables
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...