A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?

  • A. Meet with the customer to agree on the components of the solution and the priorities
  • B. Ask the sponsor for support regarding the allocation of additional resources to finish on time
  • C. Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible
  • D. Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
QuaTV
2 weeks ago
The project team is experienced & strict deadline -> Dont really need a detailed
upvoted 1 times
...
Dami77
7 months ago
Selected Answer: C
The other information provided aside "QUICKLY" are distractors. The intent is to deliver quickly, if you go too detailed as D suggested, then very unlikely you're delivering QUICKLY. With C, you will deliver quickly maybe not evrything but many MVPs
upvoted 2 times
...
odylec
8 months ago
Selected Answer: D
D is the answer
upvoted 1 times
...
CivilGuru
10 months, 2 weeks ago
D The problem is with the word delivery. Does this mean development or roll-out? I saw "delivery of a solution" as a the solution is there and it is roll-out where predictive would provide for a set plan to follow. If you see delivery as development then agile incremental and thus C.
upvoted 2 times
...
Tracyyy123
11 months, 1 week ago
Selected Answer: D
Why not D?
upvoted 1 times
...
Tuanit
11 months, 2 weeks ago
Selected Answer: D
Why shouldn't be D? Any risk with C? What if during the implementation it turns out that detail requirement/expectation are much complex than that initially assessed? "Supporting/Cooperating" doesn't mean all parties agreed to work with adaptive approach and doesn't ensure the stakeholders and client would give up their points for the shake of meeting deadline.
upvoted 1 times
...
Lucky_Cindy
12 months ago
Selected Answer: C
C. Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible
upvoted 1 times
...
Asakthi
1 year, 1 month ago
D one time delivery is key word here to go with predictive
upvoted 1 times
...
psvexam
1 year, 1 month ago
D. Customer is cooperating. So it is assumed that they will get feedback in a timely manner. Team is experienced and all are in place. All they need is a meticulous plan with all milestones, deliverables, schedules and just adhere to the plan. So best answer is D.
upvoted 3 times
...
Yuxiao
1 year, 3 months ago
Quick delivery means need to use incremental method. Incremental method ensure you to at least delivery value to customer at first, so C
upvoted 2 times
...
victory108
1 year, 3 months ago
Selected Answer: C
C. Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible
upvoted 1 times
...
AP2023S
1 year, 4 months ago
Selected Answer: D
Mmmmhhh.. How can you "ensure on-time delivery of the solution" if you have no schedule, planning etc etc? A proper planning is the first thing to do in order to be sure of the delivery timing. To use an Agile approach? Why? I don't read about any uncertainty about the scope so we can use the predictive approach...
upvoted 2 times
Jamrock
1 year, 2 months ago
The 1980's called and asked for its PM experience back. uncertainty is one aspect of using agile. Another reason is speed. (i.e. "...deployed to the public quickly).
upvoted 4 times
...
...
ANAS3796
1 year, 4 months ago
Selected Answer: C
C. Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible. By adopting an incremental delivery approach and seeking customer feedback early in the process, the project manager can obtain valuable input to guide the development and ensure alignment with the customer's requirements. This iterative approach enables early detection and resolution of any misunderstandings, potential issues, or changes in priorities, reducing the risk of rework or delays later in the project. This strategy capitalizes on the experienced project team, stakeholder support, and customer cooperation. It allows the project manager to leverage their expertise and foster collaboration between the project team and the customer throughout the development process, ensuring that the solution meets the customer's needs and expectations while maintaining a focus on timely delivery.
upvoted 2 times
...
Mobarak7
1 year, 5 months ago
Selected Answer: C
C is most appropriate as the nature of these projects
upvoted 1 times
...
Jagero_1
1 year, 6 months ago
Quick delivery = incremental way of delivery.. correct answer is B
upvoted 1 times
Jamrock
1 year, 2 months ago
Que!? what are you even saying. firs off B is wrong. secondly your statement has nothing to do with B.
upvoted 1 times
...
...
PMPNSL
1 year, 7 months ago
C- Customer feedback in the early stage is better. So over D, I'm choosing C
upvoted 1 times
...
PMPNSL
1 year, 7 months ago
C- Customer feedback in the early stage is better. So over D I'm choosing B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...