A project manager sent the first communication about the project management plan to the team. The next day, two field engineers were asking about their roles and the project schedule. What should the project manager have done?
A.
Sent the roles and responsibilities matrix along with the project management plan
B.
Confirmed that the communication was understood and solicited feedback from the team
C.
Briefed each team member on their roles before sending the project management plan
D.
Discussed the roles with the managers to help explain them to their team members
A. Send the roles and responsibilities matrix along with the project management plan to provide a clear and transparent overview of each team member's role within the project.
In addition, the project manager should:
B. Confirm that the communication was understood by soliciting feedback from the team to ensure that there are no misunderstandings and to address any questions immediately.
This combined approach ensures that the team receives all the necessary information upfront and has the opportunity to seek clarification, leading to a well-informed and cohesive project team.
As per GPT A is the correct answer and the explanation is as follows - Roles and Responsibilities Matrix: Including a roles and responsibilities matrix in the initial communication would provide clarity on what each team member is expected to do. This matrix typically outlines each team member's role, their responsibilities, and how they fit into the overall project schedule. This would prevent confusion and ensure that all team members understand their specific tasks and timelines. By including the roles and responsibilities matrix with the project management plan, the project manager would have proactively addressed the team members' questions and provided a clear framework for their roles within the project.
The best action to ensure clarity and understanding regarding roles and schedules when communicating the project management plan is:
B. Confirmed that the communication was understood and solicited feedback from the team.
Reasoning:
B. By confirming that the communication was understood and soliciting feedback, the project manager would have had an opportunity to address questions, clarify doubts, and ensure that all team members are on the same page. This is a proactive approach to ensure clarity and alignment.
B. Project Management Plan contains the project schedule as well as the resource management plan, including the R&R. A isn't correct for another reason as well - the team isn't clear on 2 things: R&R and Project Schedule; whereas the answer only suggests the PM should've sent the responsibility matrix.
How do you know in the first place that the team will ask for R&R and Project Schedule? They may ask for something else which the PM cannot foresee. Therefore B should be the correct answer, ensure feedbacks from the team are well answered.
B. Confirmed that the communication was understood and solicited feedback from the team.
While sending the project management plan to the team is a step in the right direction, it is important for the project manager to confirm that the communication was understood and provide an opportunity for the team members to ask questions or seek clarification. This can be achieved by soliciting feedback from the team and encouraging open communication channels.
By proactively seeking feedback, the project manager can gauge the team's understanding of their roles and responsibilities, as well as address any immediate concerns or questions related to the project schedule. This ensures that the team members have a clear understanding of their roles and how they fit into the project plan.
What did the first communication contain? Are we sure it contained details of responsibilities and roles? If it did not contain them then the documentation (A) must be sent and it is useless to ask for confirmation if they understood the communication if it did not contain the requested information (B). The text is ambiguous
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Rehhakles
1 month, 2 weeks agotonybuivannghia
4 months, 1 week agoShivYad
5 months, 1 week agoOnly12go
1 year, 1 month agoLucky_Cindy
1 year, 1 month agopinkwood
1 year, 2 months agoWhiteTable
1 year, 3 months agosmartrammy
1 year, 4 months agoSteAle
1 year, 5 months agoben7363728
1 year, 5 months agosassy2023
1 year, 5 months agoGoku_PMP
1 year, 3 months agoAbbasTaki
1 year, 6 months agovictory108
1 year, 6 months agoAP2023S
1 year, 6 months agoDigester
1 year, 6 months agolongge
1 year, 9 months agoJENLT
1 year, 9 months ago