Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 41 discussion

Actual exam question from PMI's PMP
Question #: 41
Topic #: 1
[All PMP Questions]

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.
What should the project manager have done to avoid this issue?

  • A. The customer's requirements should have been captured and modified to meet the supplier's standards.
  • B. The iteration review planning meeting should have been planned accordingly.
  • C. The customer's requirements should have been captured in order to meet the customer's standards.
  • D. The sprint retrospective meeting should have included necessary stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Charru
Highly Voted 2 years, 1 month ago
Its mentioned that product is delivered at the end of project life cycle, which means predictive isnt it? So "C" will be best answer.
upvoted 16 times
...
crypto_dreams_medellin
Most Recent 2 weeks ago
sprint review meetings is where the team can demo what they did, the question is what should the PM Do, meaning take an action, so the best answer i came up with is B, after picking D, changing it to D
upvoted 1 times
...
Mgaidiwahid
1 month, 3 weeks ago
Selected Answer: C
C for me
upvoted 1 times
...
Pragati06
2 months ago
It mentions project delivered at last so clearly looks it is not iterative so C will be appropriate answer.
upvoted 2 times
...
Saurav6233
6 months ago
Selected Answer: B
customer claims the product was not designed to specifications - This clearly indicates that the customer was not involved in the iteration reviews. So, it should be B
upvoted 2 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: C
C. The customer's requirements should have been captured in order to meet the customer's standards.
upvoted 2 times
...
GabMonterey
11 months, 3 weeks ago
Selected Answer: C
my answer is C
upvoted 1 times
...
Mamoonpk
1 year ago
Selected Answer: B
I will go for B This is end of project life cycle. So clearly customer didn't talk on specification during iteration reviews. Secondly, the requirement was clear unless it is stated otherwise in question
upvoted 1 times
...
ugaliwembe
1 year, 1 month ago
Selected Answer: C
I will go with C- The customer would have noted the wrong design specification during the iteration review and pointed out the issue before the product is released. Option D is wrong since it assumes the requirement was wrongly designed
upvoted 2 times
...
Omar_icon
1 year, 1 month ago
Selected Answer: C
it is predictive project (key here is the deliverables come after end of tge project)
upvoted 1 times
...
Trollem
1 year, 3 months ago
Selected Answer: B
Selected B. C suggests that requirements were captured once and it is not sufficient in my opinion.
upvoted 2 times
...
msantopietro
1 year, 4 months ago
Picked C
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: C
C. The customer's requirements should have been captured in order to meet the customer's standards
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: C
C. The customer's requirements should have been captured in order to meet the customer's standards
upvoted 1 times
...
Anna12675
1 year, 6 months ago
Selected Answer: C
voted c
upvoted 1 times
...
Faozi
1 year, 7 months ago
C. Project manager got specifications from the customer. He has to deliver what the customer wants, period
upvoted 1 times
...
shaharyarexamtopics
1 year, 8 months ago
C is correct. No need to meet supplier standards. The retro meeting is with team not with the customer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...