Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 34 discussion

Actual exam question from PMI's PMP
Question #: 34
Topic #: 1
[All PMP Questions]

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?

  • A. Meet the sponsor to ask for additional time and budget increase
  • B. Minimize the scope to catch the cost and schedule baseline
  • C. Update the project plan because the law is an obligation for the project
  • D. Assess and prioritize the impact of the new law on the project plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Selected Answer: D
We must find out how this may or may not impact the project, then we can take action as a team.
upvoted 1 times
...
Pragati06
2 months ago
Answer is D to assess and update priority on project pln
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
GabMonterey
11 months, 3 weeks ago
Selected Answer: D
D. Assessing the impact first and prioritize the highest value
upvoted 1 times
...
Tuanit
1 year, 1 month ago
Selected Answer: D
Assessment must be done first.
upvoted 1 times
...
Pranav2204
1 year, 2 months ago
Selected Answer: D
D is the answer
upvoted 1 times
...
cetinibs
1 year, 3 months ago
Selected Answer: D
Measuring impact should be the first activity.
upvoted 1 times
...
Asakthi
1 year, 3 months ago
D) - asseesment before escalation is the best PMP way
upvoted 1 times
...
AbbasTaki
1 year, 6 months ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
Anna12675
1 year, 6 months ago
Selected Answer: D
voted d
upvoted 1 times
...
BenPappoe
1 year, 7 months ago
Selected Answer: C
Voted C
upvoted 1 times
...
Ganzee
1 year, 11 months ago
D. Assess and prioritize the impact of the new law on the project plan
upvoted 3 times
...
Adeshola1960
1 year, 11 months ago
It is D because the project is yet to begin.
upvoted 2 times
...
thetailwind
2 years, 1 month ago
C and D seem nearly the same. Why D?
upvoted 1 times
longge
2 years, 1 month ago
D is prior to C. after Assess then update.
upvoted 7 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...