A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout. What should the project manager do?
A.
Meet the sponsor to ask for additional time and budget increase
B.
Minimize the scope to catch the cost and schedule baseline
C.
Update the project plan because the law is an obligation for the project
D.
Assess and prioritize the impact of the new law on the project plan
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
crypto_dreams_medellin
2 weeks agoPragati06
2 months agoBuviD
10 months, 3 weeks agoGabMonterey
11 months, 3 weeks agoTuanit
1 year, 1 month agoPranav2204
1 year, 2 months agocetinibs
1 year, 3 months agoAsakthi
1 year, 3 months agoAbbasTaki
1 year, 6 months agovictory108
1 year, 6 months agoAnna12675
1 year, 6 months agoBenPappoe
1 year, 7 months agoGanzee
1 year, 11 months agoAdeshola1960
1 year, 11 months agothetailwind
2 years, 1 month agolongge
2 years, 1 month ago