exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 34 discussion

Actual exam question from PMI's PMP
Question #: 34
Topic #: 1
[All PMP Questions]

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?

  • A. Meet the sponsor to ask for additional time and budget increase
  • B. Minimize the scope to catch the cost and schedule baseline
  • C. Update the project plan because the law is an obligation for the project
  • D. Assess and prioritize the impact of the new law on the project plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
3 days, 8 hours ago
Selected Answer: D
In my opinion , the new zoning laws have dire implication if not carefully assessed so I would suggest that the project manager take time to carefully asses the impact of the new laws on the overall cost and deliv3ery of the project early on before deployment so as to ensure that all deliverables meet the required legal requirements and any and all project cost are taken care of before the final deployment
upvoted 1 times
...
ductrinh
1 week, 5 days ago
Selected Answer: D
new law= assess then remediate asap
upvoted 1 times
...
crypto_dreams_medellin
4 months, 3 weeks ago
Selected Answer: D
We must find out how this may or may not impact the project, then we can take action as a team.
upvoted 1 times
...
Pragati06
6 months, 2 weeks ago
Answer is D to assess and update priority on project pln
upvoted 1 times
...
BuviD
1 year, 2 months ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
GabMonterey
1 year, 4 months ago
Selected Answer: D
D. Assessing the impact first and prioritize the highest value
upvoted 1 times
...
Tuanit
1 year, 6 months ago
Selected Answer: D
Assessment must be done first.
upvoted 1 times
...
Pranav2204
1 year, 6 months ago
Selected Answer: D
D is the answer
upvoted 1 times
...
cetinibs
1 year, 7 months ago
Selected Answer: D
Measuring impact should be the first activity.
upvoted 1 times
...
Asakthi
1 year, 7 months ago
D) - asseesment before escalation is the best PMP way
upvoted 1 times
...
AbbasTaki
1 year, 10 months ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
victory108
1 year, 10 months ago
Selected Answer: D
D. Assess and prioritize the impact of the new law on the project plan
upvoted 1 times
...
Anna12675
1 year, 11 months ago
Selected Answer: D
voted d
upvoted 1 times
...
BenPappoe
1 year, 11 months ago
Selected Answer: C
Voted C
upvoted 1 times
...
Ganzee
2 years, 3 months ago
D. Assess and prioritize the impact of the new law on the project plan
upvoted 3 times
...
Adeshola1960
2 years, 3 months ago
It is D because the project is yet to begin.
upvoted 2 times
...
thetailwind
2 years, 5 months ago
C and D seem nearly the same. Why D?
upvoted 1 times
longge
2 years, 5 months ago
D is prior to C. after Assess then update.
upvoted 7 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago