A project manager has been assigned with initiating a large project to deliver complex equipment. Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?

  • A. Adaptive
  • B. Hybrid
  • C. Predictive
  • D. Agile
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Digester
Highly Voted 1 year, 11 months ago
If A is the answer, why is D not the answer? So, B should be the answer.
upvoted 13 times
sassy2023
1 year, 9 months ago
Lol good one 😂
upvoted 1 times
estimater
1 year, 5 months ago
very logic
upvoted 1 times
...
...
...
ardas91
Highly Voted 2 years, 1 month ago
Selected Answer: A
Adaptive is the correct answer. This is nowhere mentioned that the first part had a predefined scope. Since the first part was a long research, that has a high chance to be iterative and the 2nd part is evident enough to be increment. Both are the part of Adaptive but not Hybrid.
upvoted 9 times
...
Julius_Dold_Learn
Most Recent 3 months ago
Selected Answer: A
Its Adaptive, See it on Page 38 of PMBOK Guide 7th.
upvoted 1 times
...
Paramak
8 months, 4 weeks ago
Selected Answer: B
A is incorrect. The other part is incrementally delivered so Hybrid.
upvoted 1 times
...
Martinussantika
10 months, 3 weeks ago
Selected Answer: B
This is hybrid: 1. Long research until completed ==> business requirement / blue prints. once this finish (predictive) 2. delivery by incremental (agile). Those two combinations call hybrid.
upvoted 2 times
...
Martinussantika
10 months, 3 weeks ago
Selected Answer: B
This is hybrid: 1. Long research until completed ==> business requirement / blue prints. once this finish then 2. delivery by incremental (agile). Those two combinations call hybrid.
upvoted 1 times
...
Musaad
1 year, 3 months ago
Selected Answer: D
D is the answer long research = iterative so, iterative + incremental = agile
upvoted 1 times
...
Bruce_Liu
1 year, 3 months ago
Selected Answer: B
Obvious Hybrid. A=D
upvoted 1 times
...
josephsafiran
1 year, 3 months ago
Selected Answer: B
The project manager should choose B. Hybrid approach for this project. A hybrid approach combines elements of both predictive (or traditional) and agile methodologies. The research part of the project, which is well-defined and can be planned out in detail, can be managed using a predictive approach. Once the research is completed, the delivery of the complex equipment, which may require flexibility and adaptability due to its complexity, can be managed using an agile approach. This allows for incremental delivery and the ability to make changes as needed based on customer feedback and changing requirements.
upvoted 3 times
...
AbouemK
1 year, 4 months ago
Research work is usual planned upfront; the deliverables are known, the expectation of stakeholders is not changing... these are all characteristics of a predictive methodology. As for phase two, it is obvious that agile is ideal. So I think answer B is best
upvoted 1 times
...
GabMonterey
1 year, 4 months ago
Selected Answer: B
B should be the answer here
upvoted 1 times
...
Mamoonpk
1 year, 4 months ago
Selected Answer: B
I see the only option Hybrid that fits. Option A and D are Adaptive/Agile which apparently works in same way however Option C is predictive. the question say it has to be in incremental in second phase. which rulesout option c and then if we take all as adaptive then it can be be either option A or Option D. the only option that is not ruled out is option B - Hybrid :D
upvoted 1 times
...
mesacgon
1 year, 5 months ago
Es hibrido, el enfoque adaptativo puede considerar (agile, incremental, iterativo) , la primera parte menciona que debe haber detalle aludiendo a algo predictivo. El enfoque adaptativo solo considera métodos agiles.
upvoted 1 times
...
Only12go
1 year, 6 months ago
Selected Answer: B
For a project where part of it relies on a long research process (which typically has a more defined and structured phase) and another part that must be incrementally delivered (which indicates a more flexible and iterative approach), the project manager should choose: B. Hybrid The hybrid approach combines elements of both traditional (predictive) and agile methodologies, which would be suitable for this project scenario.
upvoted 1 times
ChezQW
1 year, 6 months ago
In the question it was not stated that the research process of the project would be done in using a predictive or waterfall lifecycle. Due to this we can assume that the research was done iteratively with a defined scope early in the cycle. The second phase being incremental, lends to the project having an overall adaptive life cycle.
upvoted 1 times
...
...
sam1721
1 year, 7 months ago
A- Adaptive. "Adaptive project lifecycles are iterative and incremental in nature. The Agile project lifecycle approach is a special case of adaptive projects that do frequent delivery of deliverables." What is the adaptive approach in Agile? Agile and adaptive project management is a mindset and a methodology that embraces uncertainty, complexity, and change as opportunities for learning and improvement. It focuses on delivering value to customers and stakeholders through iterative and incremental processes, feedback loops, collaboration, and empowerment.
upvoted 3 times
...
Aish_
1 year, 8 months ago
Selected Answer: A
First phase requires research - Iterative Second phase - Agile When you combine iterative development with Agile principles, you essentially create an adaptive development approach.
upvoted 1 times
AbouemK
1 year, 4 months ago
Research work is usual planned upfront; the deliverables are known, the expectation of stakeholders is not changing... these are all characteristics of a predictive methodology. As for phase two, it is obvious that agile is ideal. So I think answer B is best.
upvoted 1 times
...
...
victory108
1 year, 8 months ago
Selected Answer: B
B. Hybrid
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago