A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
Aish_
Highly Voted 1 year, 3 months agocrypto_dreams_medellin
Most Recent 2 weeks, 1 day agofragar65
1 month, 2 weeks agoLotToLearn
2 months agoziyaetuk
2 months agoJMCCRAY
2 months agoOnly12go
2 months agodjgdgaf
2 months agoPragati06
2 months agoTaha1981
2 months, 1 week agoAnhHN11
4 months, 3 weeks ago723b698
5 months, 2 weeks agoAditech
7 months, 2 weeks agoBuviD
10 months, 3 weeks agoahmedzakaria
10 months, 4 weeks agoMamoonpk
1 year agougaliwembe
1 year, 1 month ago