exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 5 discussion

Actual exam question from PMI's PMP
Question #: 5
Topic #: 1
[All PMP Questions]

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?

  • A. A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
  • B. A hybrid approach will allow the project manager to revise the product specifications
  • C. A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
  • D. A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Aish_
Highly Voted 1 year, 8 months ago
Selected Answer: C
Option A suggests that the project manager chose a hybrid approach because it will enable project activities to start immediately and allow for a plan for the requirements definitions. While this statement is true to some extent, it does not fully address the specific challenges mentioned in the scenario. In the given scenario, the project manager likely chose the hybrid approach to manage both the uncertainty of unclear requirements and the fixed date restriction effectively, providing a balance between flexibility and structure. Hence, Option C aligns better with the specific challenges described in the scenario compared to Option A.
upvoted 22 times
...
Princessviv96
Most Recent 3 days, 8 hours ago
Selected Answer: C
In this case the best approach is C as it gives room to define the requirements while managing another other uncertainties as regards to the date of completion
upvoted 1 times
...
TerryV01
1 month, 2 weeks ago
Selected Answer: C
Opt c as it clarify uncertainties in a certain timeframe
upvoted 1 times
...
engamin
1 month, 3 weeks ago
Selected Answer: C
C is correct answer because is the requirement uncertainties as well as the date restriction
upvoted 1 times
...
FauziYusmin
2 months, 4 weeks ago
Selected Answer: C
In summary, the hybrid approach allows the project manager to balance adaptability and predictability, meeting the dual demands of uncertain requirements and a firm deadline.
upvoted 1 times
...
ttkong168
3 months, 3 weeks ago
Selected Answer: C
C) Allows for management of the requirement uncertainties (Agile approach) as well as the date restriction (Predictive approach to plan according to timeline)
upvoted 2 times
...
crypto_dreams_medellin
4 months, 3 weeks ago
keys: date restriction part because of the reg part (predictive) requirement uncertainly part ( agile) so C
upvoted 1 times
...
fragar65
5 months, 4 weeks ago
C. Combine Agile and Waterfall. A hybrid approach will allow for managing the requirement uncertainties while adhering to the date restriction.
upvoted 1 times
...
LotToLearn
6 months, 1 week ago
I think C is right answer as hybrid approach will allow for management of the requirement uncertainties as well as the date restriction so time line will also adhered and were its not clear it will either eventually clerarity will come or then agile/itrative approach for that particular point will help to solve issue.or if eventually clarity is obtained then Pm can continue with what ever suits better.
upvoted 1 times
...
ziyaetuk
6 months, 1 week ago
I choose C. The project manager chose a hybrid approach because it combines the advantages of both traditional (Waterfall) and Agile methodologies, allowing the team to adapt to changing requirements while still providing structure for planning, executing, and monitoring the project. By choosing a hybrid approach, the project manager can ensure that the project progresses even with unclear requirements while maintaining a focus on the regulatory deadline, ultimately delivering a product that satisfies both the customer and the organization's needs.
upvoted 1 times
...
JMCCRAY
6 months, 1 week ago
Selected Answer: C
The correct answer is C. A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction. In this situation, there are uncertainties surrounding the product definitions and requirements, but the customer wants to start the project activities as soon as possible due to a regulatory requirement for product delivery on a specific date. A hybrid approach allows for a combination of both traditional and agile project management methodologies, which can help manage the requirement uncertainties while still ensuring that the project is completed within the specified time frame. This approach provides the flexibility to adjust the project plan and requirements as needed while still maintaining a focus on meeting the delivery date requirement.
upvoted 1 times
...
Only12go
6 months, 1 week ago
Selected Answer: C
The main factors driving the decision in the scenario are: The need to manage unclear product definitions and requirements (i.e., uncertainty). The requirement to deliver by a specific regulatory date. Option A focuses more on the immediacy of starting activities and planning for requirements but does not address the constraint of the specific regulatory delivery date, which is a critical aspect of the scenario. On the other hand, option C directly addresses both the uncertainty of requirements and the date restriction, making it a more comprehensive and fitting answer.
upvoted 2 times
...
djgdgaf
6 months, 1 week ago
Selected Answer: C
I asked chat gpt and it said C: The project manager’s decision to use a hybrid approach in this scenario is driven by several factors: C. A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction. The hybrid approach provides the flexibility to adapt to evolving requirements while still adhering to the specific delivery date due to regulatory constraints. By combining elements from different methodologies, the project manager can strike a balance between structure and adaptability, managing both uncertainties and time restrictions effectively. It allows for iterative development, early progress, and ongoing adjustments as requirements become clearer. Remember, the hybrid approach is about pragmatism and tailoring the methodology to fit the project’s unique context.
upvoted 2 times
...
Pragati06
6 months, 2 weeks ago
Correct answer should be A
upvoted 1 times
...
Taha1981
6 months, 2 weeks ago
answer D
upvoted 1 times
...
AnhHN11
9 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
723b698
9 months, 3 weeks ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago