A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
Aish_
Highly Voted 1 year, 8 months agoPrincessviv96
Most Recent 3 days, 8 hours agoTerryV01
1 month, 2 weeks agoengamin
1 month, 3 weeks agoFauziYusmin
2 months, 4 weeks agottkong168
3 months, 3 weeks agocrypto_dreams_medellin
4 months, 3 weeks agofragar65
5 months, 4 weeks agoLotToLearn
6 months, 1 week agoziyaetuk
6 months, 1 week agoJMCCRAY
6 months, 1 week agoOnly12go
6 months, 1 week agodjgdgaf
6 months, 1 week agoPragati06
6 months, 2 weeks agoTaha1981
6 months, 2 weeks agoAnhHN11
9 months ago723b698
9 months, 3 weeks ago