Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 617 discussion

Actual exam question from PMI's PMP
Question #: 617
Topic #: 1
[All PMP Questions]

HOTSPOT -
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late.
Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck.
Hot Area:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Bobbie30
Highly Voted 1 year, 9 months ago
I have no idea what all of this means. Can someone please explain?
upvoted 7 times
iuedeme
6 months ago
A Kanban board is used to reduce the amount of work in progress. Looking at the board, The Specification: team are resourced to handle 4 but there are only 2 task on its cue so its fine, Coding: are resourced for 5 but they already have 4 . The specification team being over resourced would soon push another task to them which would overwhelm them. Test: is a bit tight because the have 2 task/2 resources but adequately resource utilized. Document: are 3 task/ 5 resources. From a glance at the board, one could see the coding team needs help
upvoted 1 times
iuedeme
6 months ago
Test resource needed
upvoted 1 times
...
...
...
[Removed]
Highly Voted 1 year, 11 months ago
I believe the "test" category should be selected as it seems to be the bottleneck here. The rest seem to have ample resources.
upvoted 5 times
...
Kim222
Most Recent 3 weeks ago
ANSWER IS TEST
upvoted 1 times
...
[Removed]
3 months, 2 weeks ago
The answer is Test 2
upvoted 1 times
...
certificate988
9 months, 3 weeks ago
More testing resource needed as Test is blocked.
upvoted 2 times
...
Alacosta74
11 months ago
This makes no sense to me.
upvoted 2 times
...
Only12go
11 months ago
Given this, the "Test" column is the only one that's at its maximum WIP limit, which could suggest it's where the bottleneck is occurring. If items aren't moving from the "Test" column to the "Document" column efficiently, it could delay subsequent tasks from entering the "Test" stage. To alleviate this potential bottleneck, the project manager might consider allocating additional resources to the testing phase or revising the testing process to ensure tasks move through more swiftly.
upvoted 2 times
...
janojano
11 months, 2 weeks ago
Test because this column has x2 items max and has two already, therefore no items can be pulled from the previous column until one is moved out from 'test' to 'done'
upvoted 1 times
...
victory108
12 months ago
Test one queue
upvoted 1 times
...
Dawn6699
1 year, 3 months ago
Why not Test?
upvoted 1 times
...
Graceadel
1 year, 5 months ago
test for sure Bobbie30 the kanban shows the maximum number of items that can be in the different queues. For test its 2 and they have 2 in the queue meaning nothing new can be added even *if cost can finish one item it will have to be kept at the buffer. Code can have max 5 items they have 4/5 in the queue so they not causing a bottleneck just as yet
upvoted 2 times
...
leo_gold
1 year, 9 months ago
I will go with the TEST too - When you divide # of task by # resources you get the largest number between all categories. (Tasks are the squire) (Resources are the small number under each category)
upvoted 4 times
...
Franco11
1 year, 11 months ago
The test Category
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...