A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.
How should the project manager address this situation?
Desmonddoyin
Highly Voted 1 year, 8 months agoHashi1_snr
1 year, 5 months agoPrincessviv96
Most Recent 3 days, 13 hours agolatigo
2 weeks, 2 days agoCG1111
2 months, 1 week agoDeepakuc
4 months, 3 weeks agoBuviD
1 year, 2 months agoKalhan06
1 year, 3 months agoGabMonterey
1 year, 3 months agoJames_Wild
1 year, 4 months agoMuntadher
1 year, 8 months agoHoraceZzzz
1 year, 8 months agovictory108
1 year, 10 months agoBenPappoe
1 year, 11 months agoAnna12675
1 year, 11 months agoHungdv
2 years agoHung1
1 year, 11 months agoachacyrille
2 years agoGanzee
2 years, 3 months ago