Exam PMP topic 1 question 24 discussion

Actual exam question from PMI's PMP
Question #: 24
Topic #: 1
[All PMP Questions]

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.
How should the project manager address this situation?

  • A. Use project reserves to buy new equipment to avoid an impact to the critical path of the project
  • B. Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer
  • C. Explore options with the IT department to expedite the necessary repairs based on criticality of the project
  • D. Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Desmonddoyin
Highly Voted 1 year, 8 months ago
Selected Answer: C
Negotiating is a type of soft skills a PM must posses
upvoted 8 times
Hashi1_snr
1 year, 5 months ago
I wanted to add this to the responses and found out that you have already mentioned it. This is why i agree with option C
upvoted 2 times
...
...
Princessviv96
Most Recent 3 days, 13 hours ago
Selected Answer: A
As a project manager, I will take money from the reserves to purchase a new laptop computer for the team member to avoid critical path but also report the expense for tracking purposes
upvoted 1 times
...
latigo
2 weeks, 2 days ago
Selected Answer: C
A (Using project reserves to buy new equipment) could be a last resort but is premature without trying to expedite the repairs first.
upvoted 1 times
...
CG1111
2 months, 1 week ago
Selected Answer: A
A.) because it would be a contingency? And I would cite the following: "Project reserves are special provisions for uncertainties which may affect the cost of the project. A variety of reserves should be included in the total planned cost for a long-term project as contingencies against inaccurate preliminary estimates, schedule slippage, technical problems, potential minor changes in project scope, specific events which may or may not occur, etc., and as an overall hedge against problems not anticipated at the time when the preliminary project costs were approved." --- I would like to emphasize "technical issues" from the above statement. While C sounds correct, and you would explain to the IT department that your project is critical, maybe the same approach is done by 100 of your PM colleagues each of which have the most critical project. :)
upvoted 1 times
...
Deepakuc
4 months, 3 weeks ago
Option C
upvoted 1 times
...
BuviD
1 year, 2 months ago
Selected Answer: C
C. Explore options with the IT department to expedite the necessary repairs based on criticality of the project
upvoted 1 times
...
Kalhan06
1 year, 3 months ago
Selected Answer: C
Voted C
upvoted 1 times
...
GabMonterey
1 year, 3 months ago
Selected Answer: C
C before any other option collaborating with IT dept for other solution is best way to handle the situation.
upvoted 1 times
...
James_Wild
1 year, 4 months ago
For me C can't be an option here. As long as IT teams can't provide support during 1 week due to overload, they won't be able to meet the PM to provide solutions, isn't it?
upvoted 2 times
...
Muntadher
1 year, 8 months ago
Selected Answer: C
IT department can provide the options and advise to buy or not, possible to repair or not as well.
upvoted 1 times
...
HoraceZzzz
1 year, 8 months ago
C is the best solution
upvoted 1 times
...
victory108
1 year, 10 months ago
Selected Answer: C
C. Explore options with the IT department to expedite the necessary repairs based on criticality of the project
upvoted 1 times
...
BenPappoe
1 year, 11 months ago
Selected Answer: C
Voted C
upvoted 1 times
...
Anna12675
1 year, 11 months ago
Selected Answer: A
A CORRECT
upvoted 2 times
...
Hungdv
2 years ago
I choose D.
upvoted 1 times
Hung1
1 year, 11 months ago
Change answer to C
upvoted 1 times
...
...
achacyrille
2 years ago
Selected Answer: C
The IT department say they are busy for the next one week. The best option will be to work with them to see if other options can be explored. Note that in self organising teams, they try to figure out solutions for problems themselves before reporting to the project manager. The team member have surely already tried to resolve the problem himself and have been unsucessful. So the project manager can't reforward the problem back to the team member.
upvoted 3 times
...
Ganzee
2 years, 3 months ago
B. Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago