A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.
How should the project manager address this situation?
Desmonddoyin
Highly Voted 1 year, 4 months agoHashi1_snr
1 year, 1 month agoDeepakuc
Most Recent 1 week, 4 days agoBuviD
10 months, 3 weeks agoKalhan06
11 months, 3 weeks agoGabMonterey
11 months, 3 weeks agoJames_Wild
11 months, 4 weeks agoMuntadher
1 year, 4 months agoHoraceZzzz
1 year, 4 months agovictory108
1 year, 6 months agoBenPappoe
1 year, 7 months agoAnna12675
1 year, 7 months agoHungdv
1 year, 8 months agoHung1
1 year, 7 months agoachacyrille
1 year, 8 months agoGanzee
1 year, 11 months agoarnibert
2 years agoYitrefd
2 years, 1 month agofolkmusic99
2 years, 1 month ago