Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 38 discussion

Actual exam question from PMI's PMP
Question #: 38
Topic #: 1
[All PMP Questions]

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?

  • A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule
  • B. Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project
  • C. Push out the project timeline according to the vacation plan in place based on the recent company policy
  • D. Discuss the vacation plan and include scheduling changes in the change log database
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
achacyrille
Highly Voted 1 year, 8 months ago
Selected Answer: D
Notice it didn't say all workers will go on vacation the same day or period. It simply says before the year ends. The PM in the Schedule Management during the Develope Schedule Process considers as an input the Resource Managment Plan during Aquire/allocate Resource Process developed with the help of the functional manager incharge of the resources and which usually takes into consideration such scenarios. The Vacation plan is thus discused and shedule replanned accordingly. Normally this is achieved through lags placed on activities.
upvoted 12 times
...
crypto_dreams_medellin
Most Recent 2 weeks ago
after reading the question, it said may, which means it may not, so if we schedule vacation time in a less impacting way, it may not affect time line, however, discussing the plan with the team, and them scrub it, and then take action i feel is the best way. so D and then A would be the good steps, but A i can see would be the best answer assuming D is being done inside of A
upvoted 1 times
...
Selected Answer: D
We need to understand the new policy first in order to take action
upvoted 1 times
...
Pragati06
2 months ago
D as change request is needed to be updated and tracked
upvoted 1 times
...
Bhanu2086
7 months ago
Selected Answer: A
There is a risk of schedule getting extended due to organisational announcement. So as a PM we need to come up with a risk mitigation plan rather than straightaway accomodating the schedule changes. Hence, we need to discuss with the team and come up with a plan to minimize the impact on the project schedule.
upvoted 2 times
...
hoomz
9 months, 1 week ago
Selected Answer: A
D may not be the most proactive approach compare to A
upvoted 2 times
...
kraze29
10 months, 1 week ago
Selected Answer: A
I think option A is more appropriate. If it's affecting the project timeline then before its included, need to be assure that it will have minimal impact.
upvoted 3 times
...
josephsafiran
10 months, 3 weeks ago
Selected Answer: A
I think A is the Answer Because in D if we want to update the Change Log, we need to have approval from the Board, and I know it's the company's decision and they will approve it but in some cases, the answer should mention about requesting changes Always need to communicate with the team and FM without changing things and if that doesn't give us a solution we will do the D
upvoted 2 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: A
A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule
upvoted 2 times
...
mmhawish
10 months, 3 weeks ago
Selected Answer: A
(option D) is a reactive approach and may not be effective in minimizing the impact of the vacation time on the project schedule.
upvoted 1 times
...
KIM6945
12 months ago
Selected Answer: A
ANSWER A
upvoted 1 times
...
Farooqsm
1 year ago
Question says the vacation plan may cause a change in the project time line and did not say will cause a change. So answer is D
upvoted 2 times
...
Tuanit
1 year, 1 month ago
Selected Answer: D
D Change Request is needed
upvoted 1 times
...
Exp11
1 year, 2 months ago
Selected Answer: A
Vacation time is already requested. Hence schedule changes are required. Correct ans should be D
upvoted 2 times
...
Pranav2204
1 year, 2 months ago
Selected Answer: D
D is the ans
upvoted 1 times
...
Nelsned
1 year, 2 months ago
Leaving project management techniques aside A & D both sound correct but A is more elaborate, D is vague.
upvoted 2 times
...
TienHa
1 year, 3 months ago
Selected Answer: D
D includes A that already discuss a plan with team and have a change with the minor impact.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...