A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
WhiteTable
Highly Voted 1 year, 4 months agosheilawu
10 months, 2 weeks agoActive_Learner420
Most Recent 4 days, 17 hours agoMeekMan
1 week agoActive_Learner420
4 days, 17 hours agofragar65
3 months, 1 week agoSambhav
3 months, 1 week agoHamiakz
5 months, 4 weeks agoc041644
6 months, 3 weeks ago723b698
7 months, 1 week agoKillah_B
7 months, 1 week agoompk
8 months agobinize477
9 months, 1 week agovinuuvasu
10 months, 1 week agorarehunter5
10 months, 2 weeks agoBuviD
1 year agoTony210
1 year, 1 month agoMamoonpk
1 year, 1 month agoziyaetuk
1 year, 2 months ago