A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
WhiteTable
Highly Voted 1 year, 3 months agosheilawu
8 months, 3 weeks agofragar65
Most Recent 1 month, 3 weeks agoSambhav
1 month, 3 weeks agoHamiakz
4 months, 1 week agoc041644
5 months ago723b698
5 months, 2 weeks agoKillah_B
5 months, 3 weeks agoompk
6 months, 2 weeks agobinize477
7 months, 2 weeks agovinuuvasu
8 months, 3 weeks agorarehunter5
8 months, 3 weeks agoBuviD
10 months, 3 weeks agoTony210
1 year agoMamoonpk
1 year agoziyaetuk
1 year agoestimater
1 year, 1 month agoRavi4french
1 year, 1 month ago