A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
WhiteTable
Highly Voted 1 year, 7 months agosheilawu
1 year agoPrincessviv96
Most Recent 3 days, 16 hours agoTerryV01
1 month, 2 weeks agoActive_Learner420
2 months, 3 weeks agoMeekMan
2 months, 3 weeks agoActive_Learner420
2 months, 3 weeks agofragar65
5 months, 4 weeks agoSambhav
6 months agoHamiakz
8 months, 2 weeks agoc041644
9 months, 1 week ago723b698
9 months, 3 weeks agoKillah_B
9 months, 4 weeks agoompk
10 months, 3 weeks agobinize477
11 months, 3 weeks agovinuuvasu
1 year agorarehunter5
1 year agoBuviD
1 year, 2 months agoTony210
1 year, 4 months ago