Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 469 discussion

Actual exam question from PMI's PMP
Question #: 469
Topic #: 1
[All PMP Questions]

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details.

What should be the priority order in the product backlog?

  • A. Risk 3, Risk 1, Risk 2, Requirement 3, Requirement 1, Requirement 2
  • B. Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2
  • C. Requirement 3, Requirement 1, Requirement 2
  • D. Requirement 3, Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
modsjunk
Highly Voted 1 year, 9 months ago
Selected Answer: D
Compute everything 10000 x 1 = 10000 8000 x 1 = 8000 25000 x 1 = 25000 5000 * 0.75 = 3750 4000 * 0.5 = 2000 20000 * 0.9 = 9000 Sort 25000, 10000, 9000, 8000, 3750, 2000 Match numbers to table Req3, Req1, Risk 3, Req 2, Risk 1, Risk 2
upvoted 28 times
...
emelba
Highly Voted 1 year, 5 months ago
Risks are not implemented, obviously. Only requirements. You must match each requirement with its risk in the decision tree, so: Requirement 1: 10000 - (5000*0,75)=6250 Requirement 2: 8000 - (4000 * 0,5)=6000 Requirement 3: 25000 - (20000*0,45)=9000 The answer ordered by value is C, Req3 Req 1 Req 2
upvoted 10 times
...
Uncle_Lucifer
Most Recent 10 months, 2 weeks ago
Selected Answer: D
C is flat out wrong. Risk 3 = 9000 is not > 10,000 Answer is D
upvoted 1 times
iamfrankblack
1 month, 2 weeks ago
D is wrong, you don't put risks in the backlog. Who thinks this is a thing? Risks go in the risk register. You calculate the cost of the risk and subtract it from the ROI and adjust the backlog accordingly based on the highest return.
upvoted 1 times
...
...
David983
11 months ago
Please anyone can clarify if the Project Risks must be introduced into the Product Backlog?
upvoted 2 times
Satyabrata_Paul
10 months, 4 weeks ago
You can add risk in the product backlog. It is called risk-adjusted backlog
upvoted 1 times
...
...
AmitBI
1 year ago
C. Requirement 3, Requirement 1, Requirement 2 product backlog should contain only user stories associated with each requirements. For risk, there should be a risk-adjusted backlog which will have all identified risk and their priorities and task to respond that risks.
upvoted 1 times
...
victory108
1 year ago
Selected Answer: D
D. Requirement 3, Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2
upvoted 2 times
...
Aesam
1 year, 1 month ago
Selected Answer: C
Risk can't be in product backlog
upvoted 1 times
...
rknowles
1 year, 3 months ago
Selected Answer: C
I think this is a trick question. I don't believe risks would ever be added or prioritized in the product backlog and the PMBOK says nothing about adding/tracking/assigning value to risks in the *key word* product backlog.
upvoted 2 times
...
AlekhyaT
1 year, 3 months ago
Selected Answer: D
Expected monetary value( EMV)= Risk * probability % So EMV for the risks 5000 * 0.75 = 3750 4000 * 0.5 = 2000 20000 * 0.9 = 9000 And Business value for each requirement 10000 8000 25000 So after sorting these numbers, Req3, Req1, Risk 3, Req 2, Risk 1, Risk 2
upvoted 3 times
...
Ddssssss
1 year, 4 months ago
Selected Answer: C
Weighted scoring is a Six sigma method. I have not seen weighted scoring of ROI based on risk. So I would go Req 3, Req 1, Req 2 based on value of delivery early in agile.
upvoted 3 times
...
leo_gold
1 year, 9 months ago
Selected Answer: D
You will have to multiply the priority/probability to each cost
upvoted 2 times
...
viethunggen
1 year, 9 months ago
Selected Answer: D
follow the money , should be D
upvoted 2 times
...
KA90
1 year, 10 months ago
Selected Answer: B
B seems correct
upvoted 1 times
...
Franco11
1 year, 11 months ago
Selected Answer: B
U Should Consider the value and risk, starting with Requirement 3 than the value of risk 3 = 20000 * 45% next
upvoted 4 times
...
abhijit96
1 year, 11 months ago
I think should be A. high value high risk
upvoted 1 times
...
Balaraju
1 year, 11 months ago
Any explanation pls?
upvoted 1 times
modsjunk
1 year, 9 months ago
Compute everything 10000 x 1 = 10000 8000 x 1 = 8000 25000 x 1 = 25000 5000 * 0.75 = 3750 4000 * 0.5 = 2000 20000 * 0.9 = 9000 Sort 25000, 10000, 9000, 8000, 3750, 2000 Match numbers to table Req3, Req1, Risk 3, Req 2, Risk 1, Risk 2
upvoted 1 times
...
...
kitty_kitti
1 year, 11 months ago
Why is D?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...