Exam PMP topic 1 question 335 discussion

Actual exam question from PMI's PMP
Question #: 335
Topic #: 1
[All PMP Questions]

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?

  • A. Utilize virtual teams for meetings and deliverables.
  • B. Use the contingency reserve and subcontract the work.
  • C. Review the risk register for this unforeseen circumstance.
  • D. Ask for an extension of time on the project deliverables.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
6thEditionAndy
Highly Voted 11 months, 3 weeks ago
Unforeseen circumstances are not part of the risk register, otherwise they would not be called UNforeseen circumstances. As a response to the unforeseen circumstance, which is an issue and not a theoretical risk anymore, an approriate response is virtual meetings
upvoted 5 times
...
rehan747
Most Recent 2 months, 1 week ago
C - rational "the circumstances were unforeseen, it didn't say that no face to face meetings was unforeseen as a risk.
upvoted 1 times
...
segatarasov
9 months ago
Answer A looks more logical
upvoted 1 times
...
mesacgon
1 year ago
Opino que A.
upvoted 1 times
...
[Removed]
1 year ago
Selected Answer: A
In my opinion, I think if you chose (C), you are bureaucracy Be simple !
upvoted 2 times
...
Only12go
1 year, 1 month ago
Selected Answer: A
A. Utilize virtual teams for meetings and deliverables. Given the unforeseen circumstances that prevent face-to-face meetings, the project manager should leverage technology and utilize virtual teams to facilitate communication, collaboration, and coordination among the team members. This approach allows the team to stay connected, continue work, and fulfill their individual roles without being physically present in the same location.
upvoted 3 times
...
David983
1 year, 1 month ago
Selected Answer: C
KEY SENTENCE "project is in the start-up phase of the project life cycle" Project Manager detect a RISK or a PROBLEM at the innitiating phase of the project where the risk register must be performed and where the Risk Response Plan must be defined. According to above, the common sense should be review the risk register to check if it´s registered and if not update it and set up the mitigation plan that can be A or A plus another actions.
upvoted 4 times
mdkhassan
8 months ago
Reviewing the risk register won't solve the problem at hand
upvoted 1 times
...
...
Tuanit
1 year, 1 month ago
Selected Answer: C
I go with C
upvoted 2 times
...
victory108
1 year, 3 months ago
Selected Answer: A
A. Utilize virtual teams for meetings and deliverables
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
As this is an unforeseen situation, it will not be included in the risk register.
upvoted 1 times
...
Yuxiao
1 year, 5 months ago
A is absolutely wrong. How can you confirm that virtual team works? Not every single project can work remotely. The best way is checking the risk register and acting based on existing risk response plan. So C is best fit.
upvoted 1 times
...
ardas91
1 year, 8 months ago
Selected Answer: C
The first step is to review the risk register since this was an unforeseen risk. "A" is the solution that will come as a risk response plan. Hence "C" is the best fit.
upvoted 4 times
...
Weslineo
1 year, 9 months ago
Remember that risk can be foreseen or unforeseen that is why contingencies are built into project plan.In this case we need to consult with the risk register to see if contingencies was allocated for virtual set-up fund......
upvoted 4 times
...
FlorinaP
1 year, 9 months ago
Selected Answer: A
A sounds more like a solution to me
upvoted 1 times
...
MBoo93
1 year, 10 months ago
Selected Answer: A
Answer A fits the needs
upvoted 2 times
...
Adeshola1960
1 year, 10 months ago
Selected Answer: A
The project manager should first try to establish virtual teams for meetings and deliverables as an alternative to face-to-face meetings. This will ensure that the team can still communicate and collaborate effectively.
upvoted 1 times
...
leo_gold
1 year, 11 months ago
"unforeseen circumstances" means not identifies! so it will be not registered in the risk documentation and there is no response plan for it.. I will go with A
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.