During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated with the other reports. This demonstrates a lack of teamwork and impacts project success.
What should the project manager do to resolve this issue?
arnibert
Highly Voted 1 year, 9 months agoMamoonpk
9 months, 3 weeks agosegatarasov
6 months, 3 weeks ago[Removed]
Highly Voted 2 years agorajeshtk
1 year, 11 months agoKim222
Most Recent 1 month, 1 week agoShittu1
7 months agoCommonNickname
8 months, 1 week agojosephsafiran
8 months, 2 weeks agoBruce_Liu
8 months, 3 weeks agoYh1988
10 months, 2 weeks agoChezQW
11 months agoLucky_Cindy
11 months agoDavid983
11 months, 2 weeks agos721482
11 months, 3 weeks agoFyrus
12 months agoAcmk
1 year agoGoku_PMP
1 year, 1 month agovictory108
1 year, 1 month agoMuntadher
1 year, 2 months ago