Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.
What should the project manager do next?
[Removed]
Highly Voted 2 years, 6 months agoBobbie30
2 years, 4 months agoleo_gold
2 years, 4 months agoKim222
Most Recent 7 months, 4 weeks agoDavidTri
9 months, 3 weeks agoPmpjune152024
10 months, 3 weeks agoMohammad707
1 year, 3 months agoLeoChu
1 year, 4 months agoUppersquareCapital
1 year, 3 months agocb4a6c4
1 year, 5 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agovictory108
1 year, 7 months agomiggykurkova
1 year, 7 months agoAstridN
1 year, 9 months agokevzzz
1 year, 10 months agoAbbasTaki
1 year, 10 months agoYOLO28
2 years agoYOLO28
2 years agoSynikalDemon
1 year, 9 months agoHung3102
2 years agosanjiiv
2 years, 1 month ago