Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.
What should the project manager do next?
[Removed]
Highly Voted 1 year, 11 months agoBobbie30
1 year, 9 months agoleo_gold
1 year, 9 months agoKim222
Most Recent 3 weeks agoDavidTri
2 months, 2 weeks agoPmpjune152024
3 months, 2 weeks agoMohammad707
8 months, 4 weeks agoLeoChu
9 months, 4 weeks agoUppersquareCapital
8 months, 4 weeks agocb4a6c4
9 months, 4 weeks agoOnly12go
11 months agoadingmaki
11 months, 3 weeks agovictory108
1 year agomiggykurkova
1 year agoAstridN
1 year, 2 months agokevzzz
1 year, 3 months agoAbbasTaki
1 year, 3 months agoYOLO28
1 year, 5 months agoYOLO28
1 year, 5 months agoSynikalDemon
1 year, 2 months agoHung3102
1 year, 5 months agosanjiiv
1 year, 6 months ago