Exam PMP topic 1 question 312 discussion

Actual exam question from PMI's PMP
Question #: 312
Topic #: 1
[All PMP Questions]

During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.
What should the project manager do?

  • A. Cancel the current iteration and reschedule it with the dependent activity.
  • B. Include the dependent activity in the current iteration for team B.
  • C. Ensure team B prioritizes the dependent activity in iteration three.
  • D. Assign the two critical activities to team B in iteration two.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
segatarasov
6 months, 3 weeks ago
C is a correct answer here, in my opinion
upvoted 1 times
...
psvexam
7 months, 1 week ago
Ans B: I would go with B. Why should it be assigned in Iteration 3, when we know tha A has to start in Iteration 4. And there are 2 activities. Its too much of a risk for B to start in It 4. So Answer is B
upvoted 1 times
sgsong107
2 months ago
Are we allowed to make changes during iteration? I don't think we are..
upvoted 1 times
...
...
Bruce_Liu
8 months, 2 weeks ago
Selected Answer: C
ChatGPT chooses C.
upvoted 1 times
...
Wilchim
8 months, 3 weeks ago
Selected Answer: C
I believe this question addresses the topic of servant leadership. The role of the project manager is not to impose task, but to work with the team to provide the best possible outcome. Option C meets that criteria.
upvoted 1 times
...
ChezQW
11 months ago
Selected Answer: C
I chose C because adding this activity to team B's current iteration could increase the time to complete the current iteration. There is still time to do the activity in iteration 3 in time for iteration 4.
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: C
C. Ensure team B prioritizes the dependent activity in iteration three. To address the situation where the two critical activities from team A are dependent on an activity from team B, the project manager should work on ensuring that team B prioritizes the dependent activity in the upcoming iteration, which is iteration three. This alignment in priorities will help ensure that the necessary dependencies are addressed in a timely manner, allowing team A to start their critical activities as planned in iteration four. This approach helps maintain project progress and manage dependencies effectively.
upvoted 2 times
...
AAitPMO
11 months, 2 weeks ago
B. Include the dependent activity in the current iteration for team B. as per agile , the risks to be handled as early as possible. so if dependency not handled it can turn into risk
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Ensure team B prioritizes the dependent activity in iteration three
upvoted 1 times
...
Goku_PMP
1 year, 1 month ago
Selected Answer: A
Sprint backlog ensures that it delivers the goal , the assumption that backlog can not be changes is to ensure team remains focus… but it’s a myth
upvoted 1 times
...
sshe0882
1 year, 1 month ago
I believe changes could not be added to iteration until it is completed. Iteration as well as a sprint is fixed time-box in XP Practices
upvoted 1 times
...
Thirukj
1 year, 3 months ago
C is the right answer
upvoted 1 times
...
Orochi
1 year, 3 months ago
Selected Answer: C
C During Iteration = no changes & plan next iteration
upvoted 3 times
...
AP2023S
1 year, 4 months ago
Selected Answer: C
The two tasks of team A are critical but they have to be done in iteration 4...and at the moment it is running iteration 2. So if team B task is worked on in iteration 3 there will be no problem for team A. So what's the need to change the current iteration 2 risking overloading team B?
upvoted 2 times
...
aqz_111
1 year, 4 months ago
The question mentioned 'During iteration 2' which mean the sprint has started. The sprint backlog was fixed and cannot be changed unless you have finished all the current sprint backlog and has spare time, then you can do agreed with product owner to add other user stories. Therefore, the answer is C
upvoted 1 times
...
JMCCRAY
1 year, 4 months ago
Selected Answer: C
the best course of action for the project manager in this situation is to ensure that team B prioritizes the dependent activity in iteration three. This will allow team A to begin their critical activities in iteration four as planned, without delaying the project.
upvoted 1 times
...
Alizade
1 year, 5 months ago
Selected Answer: C
C. Ensure team B prioritizes the dependent activity in iteration three. The project manager should ensure that team B prioritizes the dependent activity in iteration three, so that the two critical activities from team A can be started in iteration four as planned. By doing so, the project manager maintains the project's schedule and ensures that all dependencies are accounted for and addressed in a timely manner.
upvoted 1 times
...
emelba
1 year, 6 months ago
Option B is correct. ITERATION is the key word here, not sprint
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other