Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 304 discussion

Actual exam question from PMI's PMP
Question #: 304
Topic #: 1
[All PMP Questions]

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.
What should the project manager have done to avoid this setback?

  • A. Developed benchmarking
  • B. Assessed feasibility and impacts
  • C. Detailed the project charter
  • D. Analyzed stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks, 1 day ago
This is D
upvoted 1 times
...
akashushi007
2 months, 3 weeks ago
Selected Answer: D
D. Analyzed stakeholders This option is the most appropriate because: Stakeholder Engagement: By analyzing stakeholders, the project manager would have identified the key stakeholders, understood their interests, concerns, and levels of influence, and addressed any potential objections or questions before they became an issue. Proactive Communication: Effective stakeholder analysis allows the project manager to communicate the project's value and benefits in a way that aligns with stakeholders' interests and priorities, thereby reducing the likelihood of opposition.
upvoted 1 times
...
josephsafiran
8 months, 2 weeks ago
Selected Answer: D
The project manager should have D. Analyzed stakeholders. Stakeholder analysis is a crucial part of project planning that helps identify all parties affected by the project and understand their interests, influence, and attitudes towards the project. This understanding can help the project manager address concerns proactively, communicate effectively, and ensure that all stakeholders understand the project’s value, thereby avoiding such setbacks.
upvoted 1 times
...
6thEditionAndy
9 months, 2 weeks ago
Selected Answer: D
Its not B because you can have a perfect assessment but someone with higher power might still question it and block it if they have never been properly engaged before. Its D, because you need the buy-in from the stakeholders.
upvoted 1 times
...
Lucky_Cindy
11 months ago
Selected Answer: D
D. Analyzed stakeholders
upvoted 1 times
...
ChezQW
11 months ago
Selected Answer: B
I chose B because assessing if the project is possible and evaluating if it would actually achieve the goal of reducing production costs and placing that in the cost benefit management plan, would allow the stakeholder to see the value of the project and not have to speculate on its value. The Cost benefit management plan is an input in the develop charter process, therefore if that was done effectively the stakeholder would have been satisfied.
upvoted 3 times
...
Only12go
11 months, 1 week ago
Selected Answer: D
D. Analyzed stakeholders To avoid setbacks related to project approval and stakeholder concerns, it's important to analyze stakeholders as part of project initiation. By identifying key stakeholders, understanding their interests, concerns, and expectations, and engaging with them early in the project, the project manager can build support and address any issues or concerns they may have. This proactive approach helps ensure smoother project approval and execution. While benchmarking, assessing feasibility and impacts, and detailing the project charter are important steps in project planning and initiation, analyzing stakeholders is particularly relevant to addressing stakeholder concerns and gaining their approval.
upvoted 1 times
...
AmitBI
1 year ago
Answer should be B in my opinion. Its the initiating phase of the project and the project charter should capture all business values and associated impacts and then identify all the stakeholders and share the information to them and take approval to start the project. Analyzing stakeholders means creating stakeholder engagement plan which is to happen after the project has been successfully initiated and approved to start.
upvoted 2 times
...
victory108
1 year, 1 month ago
Selected Answer: D
D. Analyzed stakeholders
upvoted 2 times
...
TONYJAVI
1 year, 1 month ago
Selected Answer: D
I'm going with D as well. Analyze stakeholders is not only for engaging them but also to understand their priorities, their expectations and to get their support and buy-in.
upvoted 3 times
...
SteAle
1 year, 2 months ago
Selected Answer: B
as per the question, one of the stakeholder is not conveinced about the project's value. Having conducted a stakeholder analysis, would have prevented this. On the other hand, if the PM had assessed the business documentation including feasibility study and impact analysis, he could have helped the sponsor to articulate the value better
upvoted 2 times
...
TBT_1
1 year, 3 months ago
Selected Answer: B
Since the stakeholder is concerned about the value of the project, a detailed cost-benefit analysis could have improved the situation and if the feasibility was assessed properly, the questions would have been answered in the charter. Since it is in the initiation phase, the stakeholder identification is being done, and not the analysis which is performed during the planning phase.
upvoted 3 times
...
emelba
1 year, 4 months ago
Selected Answer: D
D. This proactive approach would have allowed the project manager to anticipate the concerns of the key stakeholder and address them appropriately, potentially avoiding the delay in project charter approval.
upvoted 3 times
...
aqz_111
1 year, 4 months ago
i think the answer should be B, assess the feasibility and impact. The business case documented the feasibility and impact for the manager to consider whether we should go or not go for a project. If this part is not properly done, the manager may not authorised the project or delay the approval. Therefore, the answer should be B
upvoted 2 times
Digester
1 year, 4 months ago
I agree. The question emphasizes “to lower the cost” and the stakeholder questions about the project value. B has a better logic than D as the answer.
upvoted 1 times
...
...
Alizade
1 year, 5 months ago
Selected Answer: D
The project manager should have analyzed stakeholders to avoid the setback caused by the questioning of the project's value by a key stakeholder during the approval of the project charter. By analyzing stakeholders, the project manager would have identified the stakeholders and their potential impact on the project. This would have enabled the project manager to understand the needs, expectations, and concerns of the stakeholders, including the key stakeholder, and address them accordingly in the project charter. This would have ensured that the project charter was detailed, feasible, and with fewer chances of stakeholders questioning the project's value.
upvoted 1 times
aqz_111
1 year, 4 months ago
Analyse stakeholder is for engagement. The question is approval for project charter i.e get authorisation for the existing of a project. The concern is business value for go or not go for the project, i.e impact analysis, answer D look better
upvoted 1 times
aqz_111
1 year, 4 months ago
Typo, I chose answer B
upvoted 2 times
...
...
...
Kesavaperumal
1 year, 7 months ago
A is not a right answer because there is no discussion about Product Standard D is right one
upvoted 1 times
...
leo_gold
1 year, 9 months ago
I feel A make more sense? any thoughts??
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...