Exam PMP topic 1 question 263 discussion

Actual exam question from PMI's PMP
Question #: 263
Topic #: 1
[All PMP Questions]

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant.
What should the project manager do next?

  • A. Evaluate the impact of nonrenewal of the license.
  • B. Escalate the licensing issue to the product owner.
  • C. Add a spike to the backlog for an alternative design.
  • D. Raise a change request to secure the renewal.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JMCCRAY
Highly Voted 1 year, 1 month ago
Selected Answer: A
Sounds like the correct answer is D. Raise a change request to secure the renewal. When a team member informs the project team that licenses for a component will expire in a couple of months, the project manager should take immediate action to ensure that the project is not affected. The project manager should raise a change request to secure the renewal of the license. This is important because if the license is not renewed, it may impact the project schedule, budget, and quality. ** the questions ask for what to do first so,before raising the change request, the project manager should evaluate the impact of nonrenewal of the license (Option A). **
upvoted 5 times
Hashi1_snr
7 months, 1 week ago
I can't agree with you more. The result of the evaluation will help the PM to make an accurate request for change. U analytic is so brilliant and super classic. The type of justifications that are making me love Examtopics like pure water. I love this place meh
upvoted 1 times
...
...
Martinussantika
Most Recent 3 weeks, 6 days ago
Selected Answer: D
License cost is significant, so the PM should prepare mitigate action which is option D.
upvoted 1 times
...
Tina9900
2 months, 3 weeks ago
Selected Answer: A
A. Because there is no information about the necessity of the further usage of the software. It would be possible that the software won't be used in a couple of months because the project ended. Therefore answer D would be incorrect.
upvoted 1 times
...
victory108
10 months, 3 weeks ago
Selected Answer: A
A. Evaluate the impact of nonrenewal of the license
upvoted 1 times
...
AbbasTaki
1 year ago
Selected Answer: A
Assessing the impact of the license expiration is crucial to understand the potential consequences for the project. The project manager should gather more information about the specific component, its importance to the project, and the implications of not renewing the license. This evaluation should consider factors such as the availability of alternative components, potential risks, project timelines, and cost implications.
upvoted 4 times
...
Alizade
1 year, 2 months ago
Selected Answer: A
A. Evaluate the impact of nonrenewal of the license. The project manager should first evaluate the impact of the nonrenewal of the license on the project, including the potential risks, costs, and benefits of alternative solutions. This assessment will help the project manager make an informed decision on the best course of action, whether that is renewing the license, finding an alternative component, or escalating the issue to the appropriate stakeholders.
upvoted 1 times
...
Femzy0970
1 year, 4 months ago
I’d go with D. Non renewal shouldn’t be an option cos renewal of license is a regulatory issue with dire consequences.
upvoted 1 times
...
Nickybhai
1 year, 9 months ago
Why not D?
upvoted 1 times
[Removed]
1 year, 9 months ago
Because it asks what to do next rather than what to do, you also don't know what effect the license non-renewal will have on the project. There could be a bunch of other factors, i.e. it might come out of another departments budget, funds might have been allocated already, etc. In any case, you want to evaluate/analyze/meet about the impact of something first, and thats especially important when you see the word "next" at the end of the question.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...