Question #: 412
Topic #: 1
[All PMP Questions]

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project.
What should the project manager do to enhance the success of the project?

  • A. Schedule a meeting with the new stakeholder.
  • B. Share the project status reports with the new stakeholder.
  • C. Update the stakeholder engagement plan.
  • D. Add the new stakeholder to the communications management plan.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hkcarlos
2 months, 1 week ago
Selected Answer: C
The communications management plan outlines how project communications will be conducted, but it doesn’t directly address how to engage with stakeholders. While this may eventually be done, the first and most important step is to update the stakeholder engagement plan to define how to engage with the new stakeholder effectively.
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: D
According to Lombok, there is a guide to add stakeholders and hold a dialogue or meeting.
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: A
What should project managers do to increase project success? I asked. To increase your success rate, you need to meet stakeholders.
upvoted 1 times
...
ompk
6 months, 1 week ago
as per reddit if a new stakeholder joins the project, here are the things what PM should do 1. Meet with the project sponsor to learn if new roles have been created. 2. Review the stakeholder register. 3. Submit a change request to the change control board (CCB). 4. Update the stakeholder management plan. So as per question FIRST thing to do is to update the stakeholder management plan to include the new stakeholder. THEN arrange a meeting to discuss about the project status, benefits, stakeholder's role and responsibilities etc. so in order to enhance the success of the project, PM has to start with option C.
upvoted 1 times
ompk
6 months, 1 week ago
Sorry guys , this question is very tricky. since the PM wants the new stakeholder to "AWARE" the benefits, costs, risks etc of project and the main question is how should the PM enhance the project success? so the option D is the best.
upvoted 1 times
...
...
futbool10
11 months, 4 weeks ago
Selected Answer: A
#A. The question was asking "What the PM should do to enhance the success..." Then, schedule a meeting with the stakeholder is the best possible answer. But, notice how the answer pivot to #C if the question aske "What should the PM do first to enhance..." Then, updating the stakeholder management plan is the best possible answer.
upvoted 1 times
...
David983
1 year, 1 month ago
Selected Answer: C
Just Option A won´t enhace the project Success B. Also not enough to fix the question C. Update the stakeholder engagement plan. INVOLVE THE STAKEHOLDER can improve the project success D. Add the new stakeholder to the communications management plan. Also not enough for the question
upvoted 1 times
...
kevindebruyne
1 year, 3 months ago
A --> C --> D New stakeholder so meet first
upvoted 2 times
...
Jamrock
1 year, 4 months ago
Selected Answer: A
They are all good answers in that yes you will add them to the engagement plan and communications plan BUT if you are trying to enhance success and stakeholder wants to be fully aware of goals objectives, etc. then you need to meet and discuss in detail to achieve that.
upvoted 2 times
...
chuncheon
1 year, 4 months ago
Selected Answer: A
I think A, to meet the new stakeholder's needs, you first have to do direct communication with the stakeholder.
upvoted 3 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
when a new stakeholder comes up, we need to follow all the stakeholder mgmt processes from Identify Stakeholders through Plan and Manage. The first step should be to update the risk register, then the engagement plan & comm plan. Therefore, the PM needs to meet with the stakeholder to understand their role, expectations and needs.
upvoted 3 times
...
sassy2023
1 year, 4 months ago
Selected Answer: D
I think D 1st step - add new stakeholder D 2nd step - update com plan for new stakeholder C 3rd - meet and brief new stakeholder A
upvoted 2 times
...
clarksu
1 year, 6 months ago
Selected Answer: C
update the engagement plan ,and do A . C is the right choice.
upvoted 1 times
...
clarksu
1 year, 6 months ago
Selected Answer: A
Why not directly schedule a meeting with this new stakeholder? Just add the new stakeholder in communication management plan will NOT notify the historical information such as charter and background information. You need to identify what kind of this new stakeholder would be ,and at what style/frequency you will communicate with he/she.
upvoted 3 times
clarksu
1 year, 6 months ago
I was wrong. Change to D
upvoted 1 times
clarksu
1 year, 6 months ago
I meant C, sorry
upvoted 1 times
...
...
...
PaulPMP
1 year, 7 months ago
"enhance the success " which means to do the extra mile "A"
upvoted 2 times
...
[Removed]
1 year, 8 months ago
D - Adding the new stakeholder to your communication management plan will define the "how" to communicate. Great strategy to build connection and alignment.
upvoted 2 times
...
Weslineo
1 year, 9 months ago
Correct answer should be 'A'. Meet to discuss with /update the stakeholder and them included in the communication plan going forward.
upvoted 4 times
...
PMPStudent
1 year, 11 months ago
Selected Answer: C
C is the first option you would do after a new stakeholder is identified.
upvoted 1 times
PMPStudent
1 year, 11 months ago
I change my answer, I will go with A.
upvoted 2 times
...
PMPStudent
1 year, 11 months ago
I think D is correct. lol sorry about the confusion.
upvoted 1 times
PMPStudent
1 year, 11 months ago
I dunno what is teh correct answer, apologies for the confusion
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...