Exam PMP topic 1 question 248 discussion

Actual exam question from PMI's PMP
Question #: 248
Topic #: 1
[All PMP Questions]

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely. Some team members returned to their hometowns, and they are now requesting reimbursement for operational expenditures.
What should the project manager do?

  • A. Review the budget and allocate funds for the reimbursements.
  • B. Update the project management plan with the incurred costs.
  • C. Ask the team members to draft a justification before processing the reimbursements.
  • D. Follow the Perform Integrated Change Control process and submit a change request.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
AirJordan
1 month, 1 week ago
Follow the Perform Integrated Change Control process and submit a change request. This ensures that the decision to reimburse operational expenditures is documented and approved within the project's formal change management process. It helps maintain transparency and control over budget adjustments, ensuring all stakeholders are informed and onboard with the changes. Keeping the project management plan updated with these changes is crucial for accuracy and accountability. Sensible approach, right?
upvoted 1 times
...
Abefroeman
8 months ago
Selected Answer: C
C. Ask the team members to draft a justification before processing the reimbursements. Before processing any reimbursements, it's important for the project manager to understand the nature of the operational expenditures and why they were incurred. By asking the team members to draft a justification, the project manager can ensure that the expenses were necessary and directly related to the unexpected circumstances that required remote work. This helps in maintaining accountability and transparency within the project team. Once the justifications are provided, the project manager can then proceed with reviewing the budget and processing reimbursements if deemed appropriate.
upvoted 1 times
...
josephsafiran
10 months, 2 weeks ago
Selected Answer: D
The project manager should choose option **D. Follow the Perform Integrated Change Control process and submit a change request**. In project management, any changes to the project scope, schedule, or costs should go through the Integrated Change Control process. This process ensures that all impacts of the change are considered and approved by the appropriate stakeholders before being implemented. In this case, the change in work location and the associated operational expenditures are changes that could impact the project's budget and need to be formally addressed. Please note that this is a general advice and the best course of action may vary depending on the specific circumstances and the organizational structure.
upvoted 2 times
...
Lucky_Cindy
1 year, 1 month ago
Selected Answer: D
D is correct
upvoted 1 times
...
Only12go
1 year, 1 month ago
Selected Answer: D
D. Follow the Perform Integrated Change Control process and submit a change request. In this situation, where unexpected circumstances have caused team members to work remotely and incur operational expenditures, it's advisable to follow the project's established change control process. Submitting a change request allows for a formal evaluation of the situation, potential impacts on the project budget and schedule, and a decision by the change control board or relevant stakeholders on whether to approve the reimbursement of operational expenditures. This process ensures transparency, accountability, and alignment with the project's financial and operational guidelines.
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: D
D. Follow the Perform Integrated Change Control process and submit a change request
upvoted 1 times
...
Jamrock
1 year, 4 months ago
Selected Answer: C
a CR for expenses does not sound right to me at all. i will fall on this sword if it is truly wrong. in my PM life I am NOT taking this through a change control process.
upvoted 2 times
...
ilmi
1 year, 4 months ago
In this situation, the project manager should choose option C: Ask the team members to draft a justification before processing the reimbursements. Here's what the project manager should do: Communicate with the team: Engage in open communication with the team members who are requesting reimbursement for operational expenditures. Understand the circumstances that led to the unexpected remote work and their specific expenses. Ask for justifications: Request the team members to provide justifications for the operational expenditures they are seeking reimbursement for. Ask them to provide details and supporting documentation, such as receipts or invoices, to substantiate their claims. Evaluate eligibility: Assess the justifications provided by the team members and evaluate whether the expenses incurred are reasonable and align with the project's requirements. Consider whether the expenses would have been necessary if the unexpected re
upvoted 2 times
Hashi1_snr
1 year ago
As an Internal Auditor (a CIA), i have concern for the risk of expense reimbursement fraud, where team members may submit false claims for expenses not incurred, and/or inflate expenses incurred to obtain money for personal gains. So to avert this risk from occurring the best option for the PM to take is to pass through the Change Control Board for approval of everything concerning the work process. This will save the PM from any wrongdoing or being tolerant to fraud perpetration. So option D is more strategic and best practice to do bearing in mind there is already a strategic change in the process.
upvoted 1 times
...
...
Alizade
1 year, 7 months ago
Selected Answer: D
When there are unexpected changes in the project, such as the shift to remote work and the resulting operational expenditures, the project manager should follow the Perform Integrated Change Control process. This involves submitting a change request to assess the impact of the change on the project budget, timeline, and resources. Once the change request is evaluated and approved by the appropriate stakeholders, the project manager can proceed with any necessary adjustments to the budget, project management plan, or reimbursement policies. Options A, B, and C do not follow the established change control process and may result in inaccurate budgeting or improper handling of project funds.
upvoted 4 times
...
Nivlek
1 year, 8 months ago
unexpected circumstances implies no contingency plan for this scenario, which rules out option C. I'll go with D.
upvoted 1 times
...
Trytrio
1 year, 9 months ago
Selected Answer: A
Its A. If the people got involved as requested with cost implied they must be reimbursed. There is no word mentioned that there is not enough money available for reimbursement
upvoted 1 times
...
Arulanandam
1 year, 11 months ago
Selected Answer: D
D is correct. PM cannot divert money or add money. CCB should approve. Hence ICC.
upvoted 1 times
...
Saintu
1 year, 11 months ago
D is correct, the PM cannot allocate cost that wasn’t budgeted. It normally should go through a change management process
upvoted 3 times
...
poohwinniewong
2 years ago
Why not A or B?thanks
upvoted 2 times
...
Nickybhai
2 years, 2 months ago
Why not C?
upvoted 2 times
[Removed]
2 years, 2 months ago
My first look tells me C, but it could also be D. I feel like if they wanted C, the question would use their phrasing of "what should they do next" or "what should they do first" also C seems to imply that you are making the decisions without change control board approval, depending on what they mean by "processing" I am with you though, this ones tricky, it really could be C or D, and I expect this question to be revised at some point, but D may be right as it provides more of a whole solution.
upvoted 3 times
Sumit182
1 year, 8 months ago
D is the right answer as there were " Unexpected circumstances ". So basically, an unknown- unknown & that will require a management reserve utilization for which approval has to be sought from the CCB..
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...