Exam PMP topic 1 question 223 discussion

Actual exam question from PMI's PMP
Question #: 223
Topic #: 1
[All PMP Questions]

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this knowledge in the future.
What should the agile project manager do?

  • A. Ask the team member to develop more expertise and become a subject matter expert (SME).
  • B. Ask the team member to provide a training session for the rest of the team.
  • C. Ask the team member to produce a lessons learned document and share it with the team.
  • D. Ask the team member to record highlights the team may want to know.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
alltaken
Highly Voted 2 years ago
Keyword: "For the Future". Since the knowledge is not required for other members, at least for now, the best option is to document it first and leverage on documentation later. We learn new things everyday, if everything also ask for training, then the team will not be efficient.
upvoted 23 times
TomGrey
1 year, 5 months ago
Why would you only train the team members if the knowledge is required now but not in the future?
upvoted 1 times
...
...
Fyrus
Highly Voted 1 year, 2 months ago
Selected Answer: B
IMO Lessons learned are different from creating a document about a skill, like an article about a law or a technology. It's more like "That happened, we did X and the output was Y" or share what worked and what did not work. In this case, we are talking about an ability someone have that the other don't. a masterclass and training (we are not talking about stopping the team for a week to make that) can help to share information (that's good in any case) and give good insights about the subject
upvoted 5 times
...
betterthanyesterday
Most Recent 1 day, 12 hours ago
Selected Answer: D
B. Ask the team member to provide a training session for the rest of the team. -> "training session" is not always efficient. Also, the team member may feel pressure. C. Ask the team member to produce a lessons learned document and share it with the team. -> "lessons learned document" is wrong. D. Ask the team member to record highlights the team may want to know. -> Yes, just let him first prepare materials so the team members can refer to them. A training session could be considered if necessary.
upvoted 1 times
...
AnhHN11
4 months, 4 weeks ago
Selected Answer: C
Keyword: "For the Future".
upvoted 1 times
...
ELTIGANI
6 months, 1 week ago
Selected Answer: B
B. Ask the team member to provide a training session for the rest of the team. This approach aligns with agile principles of collaboration and knowledge sharing, ensuring that the entire team benefits from the expertise of one member and can continue to work effectively and efficiently. Training sessions promote direct interaction and allow for questions and discussions, facilitating better understanding and retention of the knowledge.
upvoted 1 times
...
ompk
7 months ago
Alot of peers says "Future" means next project, but since it is agile, what about the term "future" means next sprint? and it also states that other team memebers likely to use that knowledge. Realistically, just train the other team members in case if those two decided to leave the project in the middle of the project or if the project stops etc. option B is good to go
upvoted 1 times
...
josephsafiran
11 months, 1 week ago
Selected Answer: B
The agile project manager should **B. Ask the team member to provide a training session for the rest of the team**. This approach promotes knowledge sharing and ensures that all team members have access to the information they need. It also fosters a collaborative environment where team members can learn from each other's expertise. This is in line with the principles of Agile, which emphasize individuals and interactions, as well as customer collaboration.
upvoted 3 times
...
Lucky_Cindy
1 year, 1 month ago
Selected Answer: C
C. Ask the team member to produce a lessons learned document and share it with the team.
upvoted 2 times
...
Uncle_Lucifer
1 year, 1 month ago
Selected Answer: C
training is not for future use its for immediate transfer. Answer is document lesson learned. Thank Jez I think independently. Don't just follow the crowd.
upvoted 3 times
Uncle_Lucifer
1 year, 1 month ago
meant training is not for immediate use, but for future use!
upvoted 1 times
...
...
Only12go
1 year, 1 month ago
Selected Answer: B
In an agile project, promoting knowledge sharing and collaboration among team members is crucial. When one team member is developing extensive knowledge that others may require in the future, the agile project manager should encourage knowledge transfer and team development.
upvoted 1 times
...
Tuanit
1 year, 2 months ago
Selected Answer: B
Training is the best option.
upvoted 1 times
...
nemm235
1 year, 2 months ago
Selected Answer: C
Key words in the Question: develop Knowledge in a specific matter - (team member having more knowledge about one specific matter it could be "one task". "likely" to require this knowledge - (knowledge may or may not be required for this project) So the knowledge is about a specific matter (could be a task). it should be record as a lesson learn for future use.
upvoted 3 times
...
Nemona1979
1 year, 2 months ago
Is it about agile and they use Restrospective not Lessons learnd, so I think is B.
upvoted 1 times
...
TrunkDang
1 year, 2 months ago
Selected Answer: C
C because the other team members use the document in the future.
upvoted 3 times
...
Asakthi
1 year, 4 months ago
C. Ask the team member to produce a lessons learned document and share it with the team.
upvoted 1 times
...
victory108
1 year, 5 months ago
Selected Answer: B
B. Ask the team member to provide a training session for the rest of the team
upvoted 1 times
...
SteAle
1 year, 5 months ago
Selected Answer: B
He needs to share his knowledge, not a solution to some problem
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago