Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 188 discussion

Actual exam question from PMI's PMP
Question #: 188
Topic #: 1
[All PMP Questions]

During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?

  • A. Reevaluate the backlog priority with the product owner since the velocity has been impacted.
  • B. Reevaluate the scope of the current iteration to keep the same velocity and timeline.
  • C. Reevaluate the velocity as the iteration duration will be impacted by new requirements.
  • D. Reevaluate the project schedule as the velocity will be impacted by the loss of resources.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
David983
Highly Voted 1 year, 1 month ago
Selected Answer: B
A. Backlog is priorized considering VALUE and RISK, nothing related to velocity is considered for that. so A is FULLY WRONG. B. Adjust the Scope will reduce the Work In Progress, as KANBAN, it will ensure the team keep focused correctly and keep velocity and timeline. HAVE BIG SENSE C. New Velocity will be checked by experience and testing, how many story points will be the new team able to accomplish per iteration? let´s check how it´s going on the following iterations. so no sense reevaluate as first option, the most importance is keep the team focus on work. D. Less sense than B for me.for sure Projec Schedule will suffer modifications but before change it PM will need to check for solutions like hire another team member, reduce the project scope, etc.
upvoted 10 times
...
lxplxplxp
Highly Voted 2 years ago
Selected Answer: A
if lost resource can not keep the same velocity, and check pb priority cos new requirements
upvoted 7 times
...
Amirov
Most Recent 3 weeks, 6 days ago
Selected Answer: D
A doesn't make sense, we don't reevaluate priority just because someone has left!
upvoted 1 times
...
Paramak
4 months, 1 week ago
Selected Answer: A
The answer makes no sense, without backlog priority, how can the scope be defined or even adjust??
upvoted 1 times
...
Martinussantika
6 months, 2 weeks ago
Selected Answer: A
One resource left, and topic backlog (requirement is uncovered), then time to finetune the backlog by having prioritization with product owner, which impact to velocity (how many backlogs can be finished in 1 iteration)
upvoted 1 times
...
josephsafiran
10 months, 2 weeks ago
Selected Answer: A
The project manager should **reevaluate the backlog priority with the product owner** since the velocity has been impacted (Option A). The loss of resources and the addition of new requirements will likely affect the team's velocity, or the amount of work the team can handle in a given iteration. By reevaluating the backlog priority with the product owner, the project manager can ensure that the most important tasks are still being addressed first, despite the changes. This approach maintains the focus on delivering value and meeting the project goals.
upvoted 1 times
...
mesacgon
1 year ago
Debe ser A, en agil más que cronograma se maneja backlog, eso descarta la opción B y las otras opciones no tienen sentido.
upvoted 1 times
...
Only12go
1 year, 1 month ago
Selected Answer: A
A. Reevaluate the backlog priority with the product owner since the velocity has been impacted: This approach makes sense because with reduced capacity (due to the loss of a resource) and additional requirements, it's important to prioritize which items in the backlog should be tackled next. The product owner is responsible for this prioritization.
upvoted 2 times
...
Tuanit
1 year, 1 month ago
Selected Answer: D
There is a loss of resource so the velocity of team will be impacted then the schedule.
upvoted 1 times
...
Fyrus
1 year, 2 months ago
Selected Answer: D
I don't like A since the backlog priority will not change because someone leaves the company/ team. It's like "Oh, Fredy, the developer, was fired... now this feature is less relevant to the product/company" c'mon... The only thing I is that the ITEMS inserted from the backlog into the sprint will be evaluated according to the new team's expertise and velocity...
upvoted 1 times
Fyrus
1 year, 2 months ago
Just to add: Yes, new items came out and we need to reevaluate them but it's just a normal workday. In my understanding rethinking the project's schedule is more like "OK, what's the plan now? What do we have on the backlog?"... Replan by, of course, looking at what I have to do. A is incomplete. D is not perfect but is better (IMO)
upvoted 2 times
...
...
SteAle
1 year, 4 months ago
Selected Answer: A
A. Reevaluate the backlog priority with the product owner since the velocity has been impacted - in agile projects, time and budget are fixed while the scope is flexible. Given the reduced number of resources, the project owner might want to reconsider which features he would like to have built.
upvoted 1 times
...
victory108
1 year, 5 months ago
Selected Answer: A
A. Reevaluate the backlog priority with the product owner since the velocity has been impacted
upvoted 1 times
...
emelba
1 year, 6 months ago
Selected Answer: A
A, As there are new requirements, a project backlog reevaluation is needed
upvoted 1 times
...
aqz_111
1 year, 6 months ago
D should be correct. 1. new requirements, it is required to re-priority based on business value not team's velocity so A is out 2 once the sprint is started, scope cannot be changed, it is committed by product owner and team. but the team velocity is not dropped because of reduced resource. Agile is time boxing and based on team velocity, the incompleted user stories should put back to product backlog and re-prioritized for subsequent sprint, so B is out 3 Agile length of iteration is fixed and should not be changed due to change in velocity unless it is float based but this point is not mentioned in the question so C is out 4. In Agile, scope is the user stories, now more requirements so user stories are increased but resource is reduced , we can only adjust / increase the no. of iterations so I selected D
upvoted 1 times
...
Dedutch
1 year, 7 months ago
B is maybe the worst answer not sure why it shows as correct. I like A the most but also think D is good. I think you would want to do A before updating the schedule as the velocity has changed and the new requirements may have a higher priority so the backlog should be reviewed. D takes into account the velocity reduction but not the new requirements.
upvoted 2 times
...
Hung3102
1 year, 8 months ago
In reality, I will choose D.
upvoted 1 times
...
NatieRouge
1 year, 8 months ago
Selected Answer: C
Going for option C, as the velocity should be the first metric to define before reviewing or making changes to scope or schedule.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...