A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
pigmeatpig
5 days, 21 hours agod67fcef
1 month, 1 week agoWWu
1 month, 3 weeks agoWWu
3 months, 1 week agoWWu
1 month, 3 weeks agobetterthanyesterday
3 months, 3 weeks agoductrinh
1 week, 1 day agokavikris
3 months, 4 weeks agoMartinussantika
10 months, 4 weeks agodebug91
11 months agojiljap
11 months, 1 week agodjgdgaf
1 year, 1 month agodrimz
1 year, 1 month agodrimz
1 year, 1 month agojosephsafiran
1 year, 2 months agoGabMonterey
1 year, 3 months agow_b_m
1 year, 4 months agoJaya12
1 year, 4 months agoLucky_Cindy
1 year, 5 months agoDavid983
1 year, 5 months agoDavid983
1 year, 5 months ago