exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 112 discussion

Actual exam question from PMI's PMP
Question #: 112
Topic #: 1
[All PMP Questions]

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months, but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities planned for that date were fulfilled.
How should the project manager inform the stakeholders of the project's progress?

  • A. Complete the outstanding functionalities before informing the sponsor of the project progress
  • B. Communicate the benefit expectations and the action plan for the pending functionalities
  • C. Send an email with the monthly project progress to all relevant stakeholders
  • D. Report that the project has not fulfilled all the expected functionalities
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 week, 4 days ago
Selected Answer: B
no other choice than B is correct
upvoted 1 times
...
Lucky_Cindy
6 months, 1 week ago
Selected Answer: B
Opt B is correct
upvoted 1 times
...
Asakthi
7 months, 3 weeks ago
B looks correct
upvoted 1 times
...
Muntadher
8 months, 1 week ago
Selected Answer: B
need communicate for stakeheloder
upvoted 1 times
...
victory108
10 months, 1 week ago
Selected Answer: B
B. Communicate the benefit expectations and the action plan for the pending functionalities
upvoted 1 times
...
arnibert
1 year, 4 months ago
Selected Answer: B
"benefit expectations" should be reworded with "realized benefits" to make it more understandable
upvoted 3 times
...
Nickybhai
1 year, 6 months ago
Shouldn't it be D?
upvoted 1 times
WhiteTable
7 months, 1 week ago
The project is not fully completed yet. So we cannot conclude that it didn't fulfilled the objectives.
upvoted 1 times
...
rajeshtk
1 year, 5 months ago
Need to report a combination for cost and pending items. So B is the correct answer
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago