A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?
Dinesh1987
Highly Voted 1 year, 11 months agoAcumen88
1 year, 8 months agoJanek_94
1 week, 4 days agoChymKuBoy
Most Recent 1 day, 16 hours agokavikris
2 months, 3 weeks agoduy193193
4 months, 3 weeks agoMgaidiwahid
4 months, 3 weeks agoLotToLearn
4 months, 4 weeks agoAmirov
5 months agoPragati06
5 months agoMsPigeon
9 months agoakashushi007
9 months, 1 week agoompk
9 months, 1 week agoKhoiCX
9 months, 2 weeks ago[Removed]
9 months, 2 weeks agokmsinthesky
9 months, 3 weeks agoNVHNVH
10 months, 1 week agoLNX_RM_Admin
11 months, 2 weeks agohoomz
1 year ago