A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?
Dinesh1987
Highly Voted 2 years agoAcumen88
1 year, 9 months agoJanek_94
1 month, 2 weeks agocheebooboo
Most Recent 1 week agoAjitZavade
1 month agoAjitZavade
1 month agoChymKuBoy
1 month, 1 week agokavikris
4 months agoduy193193
6 months agoMgaidiwahid
6 months agoLotToLearn
6 months agoAmirov
6 months, 1 week agoPragati06
6 months, 1 week agoMsPigeon
10 months, 1 week agoakashushi007
10 months, 2 weeks agoompk
10 months, 3 weeks agoKhoiCX
10 months, 3 weeks ago[Removed]
10 months, 3 weeks agokmsinthesky
10 months, 4 weeks ago