A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?
Dinesh1987
Highly Voted 1 year, 8 months agoAcumen88
1 year, 5 months agoduy193193
Most Recent 1 month, 3 weeks agoMgaidiwahid
1 month, 3 weeks agoLotToLearn
2 months agoAmirov
2 months agoPragati06
2 months, 1 week agoMsPigeon
6 months agoakashushi007
6 months, 2 weeks agoompk
6 months, 2 weeks agoKhoiCX
6 months, 2 weeks ago[Removed]
6 months, 2 weeks agokmsinthesky
6 months, 3 weeks agoNVHNVH
7 months, 2 weeks agoLNX_RM_Admin
8 months, 3 weeks agohoomz
9 months, 1 week agoTrytrio
9 months, 3 weeks agoBuviD
10 months, 3 weeks ago