Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 356 discussion

Actual exam question from PMI's PMP
Question #: 356
Topic #: 1
[All PMP Questions]

DRAG DROP -
In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
rajeshtk
Highly Voted 2 years, 2 months ago
Answer 1 – Proximity, 2-Connectivity, 3- Urgency, 4-Dormancy
upvoted 15 times
...
victory108
Most Recent 1 year, 3 months ago
Assess the amount of time before the risk can impact one or more project objectives --> Proximity Assess if the risk is related to other individual project risks --> Connectivity Assess how quickly the risk response needs to be implemented in order to be effective --> Urgency Assess how long after a risk has occurred before its impact is discovered --> Dormancy
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...