Actual exam question from PMI's PMP
Question #: 353
Topic #: 1
[All PMP Questions]

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations? (Choose two.)

  • A. Require a monthly individual status report
  • B. Hold daily virtual meetings to review progress
  • C. Utilize a web-based kanban board
  • D. Task functional managers to drive accountability
  • E. Implement time-keeping software for team members
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
Highly Voted 2 years, 1 month ago
Selected Answer: BC
I'm also going to say B and C because those are the only things that would improve productivity, which is what they want. You can keep track of people and get more managers involved to bug them all day, but only two things on this list increase productivity in an agile environment.
upvoted 14 times
...
ronakxaxis
Most Recent 3 weeks, 6 days ago
Selected Answer: BC
The others makes no sense
upvoted 1 times
...
d370e49
2 months, 1 week ago
Selected Answer: BC
DE are terrible choices. This is a case of a deliberately wrong or poisoned answer. It should be BC.
upvoted 1 times
...
segatarasov
8 months, 3 weeks ago
BC! Why DE??
upvoted 3 times
...
GabMonterey
11 months, 2 weeks ago
Selected Answer: BC
B&C should be the answer here
upvoted 1 times
...
Ambjord
1 year ago
What are the correct answers ?
upvoted 1 times
...
Fyrus
1 year, 1 month ago
Selected Answer: BC
Never do E... Only if you want all your devs looking for another job
upvoted 4 times
...
Sonya_123
1 year, 1 month ago
Selected Answer: BC
BC is correct
upvoted 2 times
...
victory108
1 year, 3 months ago
Selected Answer: BC
B. Hold daily virtual meetings to review progress C. Utilize a web-based kanban board
upvoted 1 times
...
Dawn6699
1 year, 5 months ago
Selected Answer: BC
Should be B and C
upvoted 2 times
...
AP2023S
1 year, 6 months ago
Selected Answer: BC
Once again the "official answer" is wrong...
upvoted 4 times
...
Dawn6699
1 year, 6 months ago
Choose B and C, DE don't make any sense.
upvoted 1 times
...
symea
1 year, 6 months ago
Is there any explanation why D and E should be correct? They don't make sense in my opinion.
upvoted 1 times
...
JMCCRAY
1 year, 6 months ago
Selected Answer: BC
B. Hold daily virtual meetings to review progress and C. Utilize a web-based kanban board are the two actions the project manager should leverage to ensure the virtual team is meeting performance expectations. Daily virtual meetings can help keep the team connected and ensure that everyone is on the same page. During these meetings, team members can review progress, discuss any challenges or roadblocks, and make any necessary adjustments to the project plan. These meetings can be done via video conferencing tools or other collaboration software. A web-based kanban board can help the team visualize the project's progress and provide transparency into what tasks are being worked on, what tasks are complete, and what tasks are still outstanding. This can help the team stay organized, track progress, and prioritize tasks more effectively.
upvoted 3 times
...
s721482
1 year, 8 months ago
really confused about the answers without a proper justification. who can recommend a reliable source to practice the PMP questions
upvoted 4 times
...
Madawu
1 year, 9 months ago
Should be B&C
upvoted 3 times
...
FlorinaP
1 year, 9 months ago
Selected Answer: BC
I agree with B & C
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...