Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 351 discussion

Actual exam question from PMI's PMP
Question #: 351
Topic #: 1
[All PMP Questions]

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?

  • A. Agree with the project team to modify and delete some of the stories in the current sprint backlog
  • B. Obtain approval from the project team and add the new story to the product backlog
  • C. Receive an agreement from the product owner and add the new story to the product backlog
  • D. Negotiate with the scrum master before adding the new story to the sprint backlog
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
Highly Voted 1 year, 12 months ago
Selected Answer: C
There's a lot wrong with this question, especially since it asks what should they do next rather than what should they have not done. Ultimately though, C is the best answer because the product owner prioritizes the backlog and not the PM.
upvoted 15 times
...
Kim222
Most Recent 3 weeks ago
Selected Answer: A
I thought C at first, but I think A is correct. The development team can modify or delete the sprint backlog. In another iteration, given the cue near the end of the sprint, the development team will analyze the sprint story.
upvoted 1 times
Kim222
3 weeks ago
This problem is very difficult... What kind of story is it? I think it's C...sorry
upvoted 1 times
...
...
segatarasov
6 months, 3 weeks ago
C must be a correct answer here, in my opinion
upvoted 1 times
...
josephsafiran
8 months, 2 weeks ago
Selected Answer: C
The project manager should C. Receive an agreement from the product owner and add the new story to the product backlog. In Scrum, the product owner is responsible for managing the product backlog. So, any changes or additions to the backlog should be made in agreement with the product owner. This ensures that the product’s vision and goals are aligned with the work being done. The team can then focus on the next sprint planning.
upvoted 1 times
...
atoms101
9 months, 1 week ago
Selected Answer: C
Since its clearly mentioned sprint has ended no action needed from team. So for next sprint for sure PO should be onboard.
upvoted 1 times
...
Lucky_Cindy
10 months, 3 weeks ago
A. Agree with the project team to modify and delete some of the stories in the current sprint backlog
upvoted 1 times
...
estimater
10 months, 3 weeks ago
Selected Answer: C
i have no idea why A is the correct answer it does not make any logic
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: C
C. Receive an agreement from the product owner and add the new story to the product backlog. In agile development, it's essential to maintain the integrity of the current sprint backlog once it has been committed to for the duration of the sprint. If a new high-priority item or change emerges during a sprint that cannot be accommodated within the current sprint's capacity, the appropriate course of action is to have the product owner evaluate and prioritize it. Once the product owner agrees and prioritizes the new feature or story, it can be added to the product backlog and considered for inclusion in a future sprint planning session. This ensures that the product owner, who represents the customer's interests, is involved in the decision-making process regarding changes to the product backlog.
upvoted 2 times
...
Fyrus
11 months, 1 week ago
Selected Answer: C
Looking at the answers it seems that the question should be "What should the PM do to avoid this problem" or "Should have done". In this case C is the right answers
upvoted 1 times
...
kevzzz
1 year ago
Selected Answer: A
In Agile the PM works with the team to get it right. The high priority requirement is already a commitment, the team must accommodate.
upvoted 2 times
...
zayn_1983
1 year ago
Selected Answer: A
the answer is A since the PM already put the new requirement in the product backlog and prioritized it as a high priority item. and finally the sprint became failed due to many uncompleted item. so the PM in the next sprint planning should consult with Product Owner to put remaining item into the top priority and agree with the team to decide and modify and delete some of the story in the sprint backlog.
upvoted 3 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Receive an agreement from the product owner and add the new story to the product backlog Should have been what should the project manager have done
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: C
It should've been "what should the project manager have done'. In this case, Answer C would make more sense
upvoted 1 times
...
Thirukj
1 year, 3 months ago
C is the right answer
upvoted 1 times
...
AP2023S
1 year, 4 months ago
Selected Answer: C
A doesn't make any sense. Why to "delete some of the stories in the CURRENT sprint backlog" if you are at the end of the sprint...?? The sprint is over and there's nothing to do with it...
upvoted 1 times
...
emelba
1 year, 4 months ago
Selected Answer: C
A is not the most appropriate because the development team does not have the authority to modify or delete user stories from the sprint backlog without the approval of the product owner. The product owner is responsible for prioritizing and managing the product backlog, including any changes to the sprint backlog. I would go with C, but something is wrong with the whole question.
upvoted 4 times
...
gramcore
1 year, 4 months ago
Selected Answer: A
The problem is that project managers have already added new features to the Sprint backlog as a high-priority item without proper analysis and planning, resulting in unfinished work on the Sprint. As a result, the project manager must take responsibility and resolve the issue. Therefore, B, C, and D, which make appropriate analysis and planning, are not correct, and A, which will solve the problem, is the answer. The project manager should work with the team to prioritize remaining tasks and make the necessary adjustments (modifications or deletions) to ensure that sprint objectives are still met.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...