A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
[Removed]
Highly Voted 1 year, 12 months agoKim222
Most Recent 3 weeks agoKim222
3 weeks agosegatarasov
6 months, 3 weeks agojosephsafiran
8 months, 2 weeks agoatoms101
9 months, 1 week agoLucky_Cindy
10 months, 3 weeks agoestimater
10 months, 3 weeks agoOnly12go
11 months, 1 week agoFyrus
11 months, 1 week agokevzzz
1 year agozayn_1983
1 year agovictory108
1 year, 1 month agoSteAle
1 year, 2 months agoThirukj
1 year, 3 months agoAP2023S
1 year, 4 months agoemelba
1 year, 4 months agogramcore
1 year, 4 months ago