Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 427 discussion

Actual exam question from PMI's PMP
Question #: 427
Topic #: 1
[All PMP Questions]

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work. The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?

  • A. Solve the issue for the team member.
  • B. Perform a brainstorming session to address the issue and add the solution to the sprint.
  • C. Escalate the issue to the software vendor for technical resolution.
  • D. Coach the team to come up with their own solution and add it to the next sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PaulPMP
Highly Voted 1 year, 7 months ago
If the solution is not added to this sprint what is the team member doing the rest of the sprint ????it clearly says ROADBLOCK ,that means it required immediate attention to be added to the backlog.so the team should have a meeting find a solution then discuss it with a product owner to add it to the spring backlog.but might be something missing from this question "due to a technical issue" but with what ? a software the team is using or where is the technical issue ? also the question stating "CRITICAL impediment " so the best possible answer for this scenario is "B"
upvoted 8 times
...
23169fd
Most Recent 1 month ago
Selected Answer: C
why not C ? If the roadblock is due to a technical issue that falls outside the team's expertise or control, escalating it to the software vendor is the most effective way to address the problem quickly. The vendor likely has the necessary knowledge and resources to resolve the issue, enabling the team to continue their work with minimal disruption.
upvoted 1 times
...
Kim222
2 months, 2 weeks ago
Selected Answer: B
It's the PM's role to resolve obstacles.
upvoted 1 times
...
CommonNickname
10 months ago
Selected Answer: A
Going with A - removing impediments for the team member
upvoted 2 times
...
xcjxcj
11 months ago
Selected Answer: D
1 technical issue no need to involve whole team. Sequence should be the team member himself -> coach -> sme -> team decision
upvoted 2 times
...
Psadon
11 months, 1 week ago
Selected Answer: D
This option emphasizes empowering the team to find a solution collaboratively. By coaching the team to address the technical issue themselves, it promotes ownership, teamwork, and self-organization within the Agile framework.
upvoted 2 times
...
Hashi1_snr
1 year, 1 month ago
Selected Answer: B
Without doing B, there will still be impediments that will negativity impact the project. The brainstorming session will help the PM to identify which area (s) requires coaching. It's a step in risk identification process that helps in determining response strategies for the impediment.
upvoted 2 times
...
Only12go
1 year, 1 month ago
Selected Answer: B
Between B or D, B is more productive and direct.
upvoted 1 times
...
David983
1 year, 1 month ago
Selected Answer: B
Although the Sprint Goal is fixed during the Sprint, the Sprint Backlog is not. Need to add the corrective actions into the current sprint backlog in order to be able to accomplish the sprint goal
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: B
B. Perform a brainstorming session to address the issue and add the solution to the sprint
upvoted 1 times
...
TONYJAVI
1 year, 3 months ago
Selected Answer: B
At first I was going to go for D as you don't typically add/remove items from the sprint backlog, but after thinking it through, better answer is B. There are some exceptions to change items in the sprint backlog like if a critical defect is discovered during the Sprint that requieres immediate attention, the team may decide to include them in the Sprint Backlog to fix them, not waiting until the next iteration. Also, the sprint Goal should be reviewed.
upvoted 2 times
...
SteAle
1 year, 4 months ago
Selected Answer: B
If the roadblock prevents the team from meeting the sprint goal, the issue needs to be addressed first. Myth: The Sprint Backlog can't change during the Sprint https://www.scrum.org/resources/blog/myth-2-sprint-backlog-cant-change-during-sprint#:~:text=Myth%3A%20The%20Sprint%20Backlog%20can't%20change%20during%20the%20Sprint&text=The%20Development%20Team%20commits%20itself,to%20fulfil%20their%20given%20commitment.
upvoted 2 times
SteAle
1 year, 4 months ago
Scrum Guide: "The Sprint Goal is created during the Sprint Planning event and then added to the Sprint Backlog. As the Developers work during the Sprint, they keep the Sprint Goal in mind. If the work turns out to be different than they expected, they collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint without affecting the Sprint Goal."
upvoted 1 times
...
...
[Removed]
1 year, 5 months ago
My answer "C"- It is the PM's role to remove impediments being a servant leader so that the team can continue with the sprint goal. Any thoughts?
upvoted 2 times
...
duyun
1 year, 6 months ago
Selected Answer: D
Agile first teams solve problems themselves.
upvoted 1 times
...
RevZig67
1 year, 7 months ago
Selected Answer: A
As the project manager, it is the responsibility to help remove any impediments that are blocking the team from progressing. In this case, the roadblock is due to a technical issue, so the project manager should help solve the issue for the team member so that they can continue with their work. This will ensure that the team remains productive and the sprint progress is not hindered. Option B suggests a brainstorming session to address the issue, which might take time and could delay the progress of the sprint. Option C involves escalating the issue to a third-party software vendor, which may not be feasible, especially if the vendor is not immediately available to resolve the issue. Option D involves coaching the team to come up with their own solution, which may not be appropriate for a critical impediment that is blocking the team's progress.
upvoted 3 times
CommonNickname
10 months ago
Also going with A - removing impediments for the team member
upvoted 1 times
...
...
Hung3102
1 year, 7 months ago
B is ans
upvoted 2 times
...
sanjiiv
1 year, 8 months ago
Selected Answer: D
B is wrong since nothing should be added during the sprint. Any new requirements or changes should be done in the next sprint.
upvoted 2 times
Jamrock
1 year, 3 months ago
wrong. this is not new or a change. it is an issue (roadblock).
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...