During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project.
What should the project manager do?
modsjunk
Highly Voted 1 year, 6 months agoUppersquareCapital
Highly Voted 5 months, 2 weeks agoSugansivram
Most Recent 5 days, 12 hours agovictory108
9 months, 3 weeks agoAish_
10 months, 2 weeks agoJame
12 months agoAbbasTaki
1 year agosegatarasov
3 months, 2 weeks agonoppy
1 year agomangostiffy
1 year, 1 month agoWeslineo
1 year, 3 months agoKA90
1 year, 7 months agorajeshtk
1 year, 9 months ago[Removed]
1 year, 8 months agoBobbie30
1 year, 6 months agoleo_gold
1 year, 6 months ago