During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project.
What should the project manager do?
modsjunk
Highly Voted 1 year, 10 months agoUppersquareCapital
Highly Voted 9 months, 3 weeks agoSugansivram
Most Recent 4 months, 1 week agovictory108
1 year, 1 month agoAish_
1 year, 2 months agoJame
1 year, 4 months agoAbbasTaki
1 year, 4 months agosegatarasov
7 months, 3 weeks agonoppy
1 year, 4 months agomangostiffy
1 year, 5 months agoWeslineo
1 year, 8 months agoKA90
1 year, 11 months agorajeshtk
2 years, 1 month ago[Removed]
2 years, 1 month agoBobbie30
1 year, 11 months agoleo_gold
1 year, 10 months ago