During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?
[Removed]
Highly Voted 2 years, 7 months agoKim222
Most Recent 7 months, 4 weeks agomrwriting
1 year agoBruce_Liu
1 year, 2 months agoOnly12go
1 year, 6 months agovictory108
1 year, 7 months agoAish_
1 year, 8 months agoJesusisreal
1 year, 9 months agoDawn6699
1 year, 10 months agocwilson91
1 year, 10 months agoHung3102
2 years agomeetkamal
2 years, 1 month agoWeslineo
2 years, 2 months agoWeslineo
2 years, 2 months agoPMPStudent
2 years, 4 months agomjs
2 years, 5 months agoFranco11
2 years, 6 months agorajeshtk
2 years, 7 months ago